HORIZON
Share

SHRI CAPITAL APARTMENT 3

P53100050550 · MahaRERA · https://gethorizon.in/projects/shri-capital-apartment-3-sangli-miraj-kupwad-m-ukqb9e9e

Registration lapsed

This project’s MahaRERA registration has lapsed— it expired and was not renewed. A lapsed project may be stalled, finished-but-not-updated, or abandoned; the record stops here and RERA’s ongoing protections may no longer apply. Confirm the current status directly with MahaRERA before you rely on anything below.

01

Complete project overview

MahaRERA · Registration filing
Units
23 units
Floors
6
Buildings
2
Parking
15 spaces
Land area
473 sq m
Sanctioned built-up
1,177 sq m

Timeline

RERA registeredApr 2023
Proposed completionDec 2025
TodaySep 2026
02

Builder’s track record

MahaRERA · Builder registration

SHRISAMARTH DEVELOPERS

PartnershipPromoter type
Sangli, MAHARASHTRABased in
1Projects
1City
2023–2025Active
Timelineevery project, start → promised completion

The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Sangli Miraj Kupwad (M Corp.)
Taluka
Miraj
District
Sangli
Pincode
416416
Survey no.
C S NO 4062
North boundary
18 Mtr ROAD
East boundary
C S NO 4061
South boundary
C S NO 4060
West boundary
C S NO 4063
What’s nearby
Schools1 school within 1km
HealthcareHospital 1.1km away · 1 clinic within 1km
LifestylePark 997m away · 3 restaurants and cafes within 1km
ShoppingNo supermarket within 2km · Bank 991m away
Getting around
Expressway 787 m · Sangli-Miraj RoadPrimary road 1.6 km · Kupwad MIDC RoadRailway line 1.1 kmRailway station 613m away (Vishrambag)Limited bus connectivity nearby
Water & environment
Water body 1.6 km · Water Purification Plant
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra registration department

In Maharashtra it’s called the ready reckoner rate.

No government guidance rate is shown for this project.

Maharashtra's schedule is in Horizon's record, but this project's filed location couldn't be matched to one place with certainty — so no figure is shown rather than a guess.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

MahaRERA · Approved building plan

Sangli Miraj Kupwad Municipal Corporation

Municipal Corporation
Building Permit
Survey no. C S NO 4062

The promised possession date (31 Dec 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Sangli Miraj Kupwad Municipal Corporation

Municipal corporation

Has approved 48 RERA projects0.2% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
44
On record
274 flats · 0 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by MahaRERA

07

Other projects nearby

The register · within 25 km

123 residential projects still under way within 25 km. Step out ring by ring:

5 projects within 1 km — showing the nearest 5.

Sangli Miraj KupwadResidential / Group Housing

Siddhivinayak-Laxmi

Balaji Associates

Apr 2024registered
Sep 2026target completion
Scale21 flatsAuthorityMahaRERA
Sangli Miraj KupwadOthers

SHRIPAD VALLABH SIDDHI

ASSOCIATED DEVELOPERS

Dec 2024registered
Oct 2027target completion
Scale40 flatsAuthorityMahaRERA
Sangli Miraj KupwadOthers

GOVIND ICON

G.K. ASSOCIATES

Jun 2021registered
Dec 2026target completion
Scale161 flatsAuthorityMahaRERA
Sangli Miraj KupwadResidential / Group Housing

OJAS 2

VISA DEVELOPERS

Dec 2024registered
May 2027target completion
Scale18 flatsAuthorityMahaRERA
Sangli Miraj KupwadOthers

SHRI KRUPA ICON

TATYASAHEB SAMBHAJI KHOT

Feb 2024registered
Nov 2026target completion
Scale36 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. This project’s coordinate is approximate, so distances are rough.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.