Complete project overview

MahaRERA · Registration filing
Units
36 units
Mix
26 × 2 BHK · 8 × Shop · 2 × 1 BHK
Carpet area
14–66 sq mper-unit range, as filed
Floors
7
Parking
45 spaces
Land area
584 sq m
Sanctioned built-up
1,495 sq m

Timeline

RERA registeredFeb 2024
Proposed completionNov 2026
TodayJul 2026
Construction progress
Podiums0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Electrical meter r…0%
Open Parking0%
Internal finishes25%
Water Supply50%
Excavation100%
Basement (if any)100%
Plinth100%
Stilt floor100%
Superstructure100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

36 units across 18 batches
TypeArea sq mCount
2 BHK601
2 BHK591
1 BHK661
Shop211
2 BHK601
1 BHK661
2 BHK664
2 BHK652
2 BHK581
2 BHK611
Shop261
2 BHK639
Shop291
2 BHK624
Shop143
Shop202
2 BHK601
2 BHK611

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

MahaRERA · Promoter registration

TATYASAHEB SAMBHAJI KHOT

IndividualPromoter type
Sangli, MAHARASHTRABased in
6Projects
1City
2020–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
77 homeson the public record across 6 projects
6,938 sq mbuilt-up filed
5,073 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Sangli Miraj Kupwad (M Corp.)
Taluka
Miraj
District
Sangli
Pincode
416415
Survey no.
NEW S NO 144/1 (OLD S NO 192/1) PLOT NO 43
North boundary
PLOT NO 41
East boundary
S NO 191
South boundary
GOVT ROAD
West boundary
COLONY ROAD
What’s nearby
SchoolsNearest school 1.0km away
HealthcareHospital 239m away · 3 clinics within 1km
LifestylePark 1.0km away
ShoppingNo supermarket within 2km · Bank 973m away
Getting around
Expressway 803 m · Sangli-Miraj RoadPrimary road 919 m · Kupwad MIDC RoadRailway line 749 mRailway station 506m away (Vishrambag)Limited bus connectivity nearby
Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.