01
Complete project overview
MahaRERA · Registration filing- Floors
- 5
- Buildings
- 2
- Parking
- 28 spaces
- Land area
- 629 sq m
- Sanctioned built-up
- 799 sq m
Timeline
RERA registeredApr 2026
Proposed completionMar 2027
TodayJul 2026
Construction progressPer-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
Stilt floor0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Water conservation…0%
Energy managemcnt0%
Fire protection an…0%
Electrical meter r…0%
Excavation100%
Plinth100%
Superstructure100%
02
Builder’s track record
MahaRERA · Promoter registrationShri Vinayak Construction
PartnershipPromoter type
Pune, MAHARASHTRABased in
3Projects
2Cities
2019–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
477 plotson the public record across 3 projects
799 sq mbuilt-up filed
629 sq mland declared
₹7.33 Crdeclared build cost
Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.
Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
03
Location
MahaRERA · Registration filing- Village
- Wadagaon (CT)
- Taluka
- Mawal
- District
- Pune
- Pincode
- 412106
- Survey no.
- plot_no 2 AND 3 city_survey_gut_no S.NO 5/1 final_plot_no - sector_no - mauje WADGAON road_street 30MTR society -
- North boundary
- Survey No 5
- East boundary
- Plot No 1, Survey No 5
- South boundary
- 9 Mtr Road
- West boundary
- DP Road
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 825m away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km · Bank 631m away
Getting around
Expressway 873 m · Mumbai - Pune Expressway (Toll Road)Primary road 3.3 km · Urse Talegaon RoadRailway line 431 m · Mumbai–Pune RailwayRailway station 516m away (Vadgaon)Limited bus connectivity nearby
Water & environment
Water body 527 mRiver 1.8 km · Indrayani
distances only — not a flood assessmentLegal & regulatory recordFrom MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
LitigationNone declared to MahaRERA
None on record with MahaRERA against this project.
Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.
What this record cannot tell you
- Build quality — no filing records how well it was actually built.
- Private disputes — only complaints escalated to the authority appear here.
- What it will be worth — the record is the past; it does not price the future.