HORIZONMarkets
01

Complete project overview

WBRERA · Registration filing
Apartments
18
Land area
498 sq m
Built-up area
789 sq m
Carpet area
725 sq m
Parking
6 spaces
RERA registered
2024

Timeline

RERA registeredJan 2024
Proposed completionMar 2026
TodayJul 2026
02

Builder’s track record

WBRERA · Promoter registration

SURESH AGARWAL HUF

IndividualPromoter type
Kolkata, West BengalBased in
3Projects
1City
2024–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
32 homeson the public record across 3 projects
1,698 sq mbuilt-up filed
1,015 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

WBRERA · Registration filing
District
Kolkata
Police station
Behala
Address
797A PASHUPATI BHATTACHARJEE ROAD
Pincode
700041
What’s nearby
SchoolsNearest school 1.3km away · College or university 796m away
HealthcareHospital 1.3km away · 1 clinic within 1km
LifestylePark 1.5km away
ShoppingSupermarket 1.5km away · Mall 1.7km away · Convenience store within 1km
Getting around
Expressway 1.6 km · Diamond Harbour RoadPrimary road 1.4 km · Deshapran Sashmal RoadRailway line 1.9 km · Ballygunge Junction-Budge BudgeMetro station 1.4km away (Mahanayak Uttam Kumar)Limited bus connectivity nearby
Water & environment
Water body 119 mRiver 871 m · Adi Ganga
distances only — not a flood assessment
04

Planning authority

WBRERA · Approved building plan

Kolkata Municipal Corporation

Municipal Corporation
Building Permit

The promised possession date (31 Mar 2026) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Kolkata Municipal Corporation

Municipal corporation / municipality

Has approved 1,030 RERA projectsabout 1 in 2 in West Bengal, more than any other body in the state.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
776
On record
14,568 flats · 0 plots
Reach
5 districts

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Compliance & litigation record
Defaulter listThis developer appears on WBRERA's defaulter list
WBRERA lists the developers it has flagged as defaulters — that line is the authority's own record; any litigation line is the promoter's own declaration at registration. A flagged line is worth verifying directly with WBRERA; none of it is a verdict on the project.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — WBRERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — WBRERA does not publish a complaints register. This read cannot speak to them either way.
  • Escrow — WBRERA does not publish escrow declarations. Whether buyer money is ring-fenced cannot be read here.