Complete project overview

MahaRERA · Registration filing
Floors
9
Buildings
2
Parking
109 spaces
Land area
1,000 sq m
Sanctioned built-up
3,907 sq m

Timeline

RERA registeredMar 2024
Proposed completionDec 2026
TodayJul 2026
Construction progress
Podiums0%
Stilt floor0%
Internal Roads & F…0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Street Lighting0%
Water conservation…0%
Energy managemcnt0%
Fire protection an…0%
Electrical meter r…0%
Open Parking0%
OC-readiness4%
Flat fit-out25%
Internal finishes64%
External finishes89%
Stairs & lifts95%
Excavation100%
Basement (if any)100%
Plinth100%
Superstructure100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

SOHAM DEVELOPERS

PartnershipPromoter type
Pune, MAHARASHTRABased in
14Projects
7Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
688 homeson the public record across 14 projects
23,868 sq mbuilt-up filed
29,935 sq mland declared
₹140.70 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Rajkot Municipal CorporationMunicipal / Corporation3 of 9 projects
Pimpri Chinchwad Municipal CorporationMunicipal Corporationthis project2 of 9 projects
Surat Municipal CorporationMunicipal / Corporation2 of 9 projects
Others1 of 9 projects
Vadodara Urban Development AuthorityUrban Development Authority1 of 9 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Tathwade
Taluka
Mulshi
District
Pune
Pincode
411033
Survey no.
42/2(P)
North boundary
BY 20 FT WIDE PUBLIC ROAD
East boundary
BY PROPERTY OF VIJAY BHOSALE FROM SNO 42 2
South boundary
BY PROPERTY OF SANDEEP RAMAN PAWAR SNO 43 3
West boundary
BY PROPERTY BEARING SNO 42 2
What’s nearby
Schools2 schools within 1km
HealthcareHospital 537m away · 2 clinics within 1km
LifestyleNo parks within 2km · Gym or sports centre 596m away · 7 restaurants and cafes within 1km
ShoppingSupermarket 549m away
Getting around
Expressway 1.2 kmPrimary road 368 m · Shree Chatrapati Shivaji Maharaj FlyoverRailway line 3.3 km · Mumbai–Pune RailwayMetro station 3.0km away (Wakad Chowk metro Station)Limited bus connectivity nearby
Water & environment
Water body 666 m · silver jym swimming poolRiver 1.2 km · Pavana River
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Pimpri Chinchwad Municipal Corporation

Municipal Corporation
Building Permit
Survey no. 42/2(P)
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Pimpri Chinchwad Municipal Corporation

Municipal corporation

Has approved 1,391 RERA projectsabout 1 in 14 in Maharashtra.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,080
On record
9,009 flats · 249 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.