HORIZON
Share

Solitaire Edge

P51800030831 · MahaRERA · https://gethorizon.in/projects/solitaire-edge-borivali-07itpmf0

01

Complete project overview

MahaRERA · Registration filing
Units
127 units
Floors
43
Buildings
2
Parking
111 spaces
Land area
5,821 sq m
Sanctioned built-up
9,283 sq m

Timeline

RERA registeredSep 2021
Proposed completionDec 2026
TodaySep 2026
Construction progress
Basement (if any)0%
Excavation100%
Podiums100%
Plinth100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
OC-readiness100%
Water Supply100%
Sewerage (Chamber,…100%
Storm Water Drains100%
Landscaping & Tree…100%
Treatment And Disp…100%
Solid Waste Manage…100%
Water conservation…100%
Energy managemcnt100%
Electrical meter r…100%
Fire protection an…1000%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Builder registration

MAHAVEER CONSTRUCTION

PartnershipPromoter type
Mumbai Suburban, MAHARASHTRABased in
1Projects
1City
2021–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Borivali
Taluka
Borivali
District
Mumbai Suburban
Pincode
400101
Survey no.
CTS NO 3pt, 4pt, 5pt, 6pt and 7pt
North boundary
EXISTING SUHAS MODI ROAD
East boundary
CTS NO 8
South boundary
27 45 MTR WIDE DP ROAD RAJGURU FLYOVER
West boundary
CTS NO 3
What’s nearby
SchoolsNearest school 1.5km away
HealthcareHospital 236m away · Clinic within 2km
Lifestyle1 park within 500m · Playground within 500m · 4 restaurants and cafes within 1km
ShoppingSupermarket 949m away · Mall 1.4km away · Bank 978m away
Getting around
Expressway 1.0 km · Mahindra FlyoverPrimary road 2.6 km · Swami Vivekanand RoadRailway line 2.1 kmMetro station 1.2km away (Poisar)Bus stop within 1km
04

Government Guidance Rate

Maharashtra registration department

In Maharashtra it’s called the ready reckoner rate.

No government guidance rate is shown for this project.

Mumbai's ready reckoner is addressed by city survey (CTS) number inside a named village, and this filing declares neither — its village field holds a ward or a taluka. Naming one of the zones around it would be a guess, and inside a single division the rates run three-fold.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

MahaRERA · Approved building plan

Slum Rehabilitation Authority

Slum Rehabilitation Authority
Building Permit
Survey no. CTS NO 3pt, 4pt, 5pt, 6pt and 7pt
The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Slum Rehabilitation Authority

Planning authority

Has approved 729 RERA projects3.6% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
554
On record
15,389 flats · 0 plots
Reach
4 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by MahaRERA

07

Other projects nearby

The register · within 25 km

4,201 residential projects still under way within 25 km. Step out ring by ring:

18 projects within 1 km — showing the nearest 6.

AkurliResidential / Group Housing

Mahindra Vista Phase 1

Mahindra Lifespace Developers limited

Feb 2024registered
Dec 2029target completion
Government Guidance Rate₹1,20,728/sq ydScale601 flatsAuthorityMahaRERA
AkurliOthers

Mahindra Vista Phase 2

Mahindra Lifespace Developers limited

Feb 2025registered
Dec 2030target completion
Government Guidance Rate₹1,20,728/sq ydScale667 flatsAuthorityMahaRERA
Pahadi-GoregaonResidential / Group Housing

RIVIERA

Meghna Aakar Constructions

Dec 2024registered
Mar 2027target completion
Government Guidance Rate₹1,47,593/sq ydScale35 flatsAuthorityMahaRERA
Pahadi-GoregaonOthers

SHETH SQUARE

SHETH BUILDERS PRIVATE LIMITED

Jul 2024registered
May 2029target completion
Government Guidance Rate₹1,35,001/sq ydScale68 flatsAuthorityMahaRERA
BorivaliResidential / Group Housing

SAVANA PHASE - 3

SIMBA PROPERTIES LLP

Dec 2019registered
Jun 2027target completion
AuthorityMahaRERA
AkurliResidential / Group Housing

AVASA

KOLTER REALTY LLP

Aug 2026registered
Dec 2031target completion
AuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. This project’s coordinate is approximate, so distances are rough.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.