01

Complete project overview

RERA Telangana · Registration filing
Units
10 units
Unit mix
10 × 3BHK
Saleable area
142–146 sq mper unit, as filed
Floors
5
Land area
511 sq m
Built-up area
1,479 sq m

Timeline

RERA approvedSep 2019
Proposed completionOct 2024
TodayJul 2026
Construction progress

56% overall, as filed

Podiums0%
External finishes10%
Flat fit-out20%
OC-readiness20%
Stilt floor60%
Stairs & lifts70%
Internal finishes80%
Excavation100%
Basement & plinth100%
Superstructure100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

10 of 10 available
BuildingFloorTypeArea sq mAvailable
SRI LEKHA ENCLAVE13BHK1461 of 1
SRI LEKHA ENCLAVE13BHK1421 of 1
SRI LEKHA ENCLAVE23BHKmortgaged1461 of 1
SRI LEKHA ENCLAVE23BHKmortgaged1421 of 1
SRI LEKHA ENCLAVE33BHK1461 of 1
SRI LEKHA ENCLAVE33BHK1421 of 1
SRI LEKHA ENCLAVE43BHK1461 of 1
SRI LEKHA ENCLAVE43BHK1421 of 1
SRI LEKHA ENCLAVE53BHK1461 of 1
SRI LEKHA ENCLAVE53BHK1421 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

SRI VENKATESHWARA CONSTRUCTIONS

PartnershipPromoter type
Medchal-Malkajgiri, TelanganaBased in
12Projects
5Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
362 homeson the public record across 12 projects
62,405 sq mbuilt-up filed
39,276 sq mland declared
₹75.00 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Greater Hyderabad Municipal Corporation (GHMC)Municipal / Corporationthis project5 of 10 projects
Hyderabad Metropolitan Development Authority (HMDA)Urban Development Authority3 of 10 projects
BDA - Bangalore Development AuthorityUrban Development Authority1 of 10 projects
Directorate of Town & Country Planning (DTCP)Town & Country Planning (DTCP)1 of 10 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
HANUMAN NAGAR
Village
Hanumanagar
Mandal
Saroornagar
District
Ranga Reddy
Pincode
500068
North boundary
ROAD
East boundary
ROAD
South boundary
PLOT NO 30
West boundary
PLOT NO 29
What’s nearby
SchoolsNearest school 1.2km away
HealthcareHospital 495m away · Clinic within 2km
LifestyleNo parks within 2km · Gym or sports centre 971m away
ShoppingSupermarket 43m away · Mall 1.6km away
Getting around
Expressway 971 m · Inner Ring RoadPrimary road 2.0 km · Inner Ring RoadRailway line 2.8 km · chaitanyapuri metroMetro station 2.3km away (L. B. Nagar Metro Station)Bus stop within 500m
Water & environment
Water body 227 m
distances only — not a flood assessment
Declared external development
Sewerage (Chamber,…30%
Electricity30%
Rainwater20%
Renewable energy10%
Roads0%
Water supply0%
Rainwater0%
Green Strip/TOT LO…0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Fire safety0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Greater Hyderabad Municipal Corporation (GHMC)

Municipal / Corporation
Building Permit
Survey no. 14/1 AA & 14/5AA

The promised possession date (1 Oct 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

GHMC

Municipal Corporation · Hyderabad city core

Has approved 3,102 RERA projectsabout 1 in 4 in Telangana.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,994
On record
2,20,211 flats · 3,387 plots
Reach
65 mandals
Since
2016

More apartment-heavy than Telangana overall — 99% apartments here vs 66% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.