Subramaniyapuram Colony Scheme

TN/20/Building/0473/2024 · TNRERA · https://gethorizon.in/projects/subramaniyapuram-colony-scheme-k5twrw46

01

Complete project overview

TNRERA · Registration filing
Description
Registration for Stilt Floor + 9 Floors residential building with 396 Tenements at Subramaniapuram. Comprised in Old T.S.No. 21 Part , New T.S.Nos. 40 , 42 , Ward - IV , Block - 39 of Madurai Town , Madurai West Taluk , Madurai District.
Registration no.
TN/20/Building/0473/2024

Timeline

RERA registeredSep 2024
Proposed completionMar 2025
TodaySep 2026
02

Builder’s track record

TNRERA · Builder registration

Tamil Nadu Urban Habitat Development Board

Tamil Nadu Urban Habitat Development BoardPromoter
5Projects
1Cities
2024–2025Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
5 projectson the public record across 5 projects

These are sums of what the builder has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
CMDA (Chennai Metropolitan Development Authority)CMDA (Chennai Metropolitan Development Authority)4 of 5 projects
Town & Country Planning (DTCP)Town & Country Planning (DTCP)this project1 of 5 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from Tamil Nadu Urban Habitat Development Board— the full portfolio →

03

Location

TNRERA · Registration filing
What’s nearby
Schools1 school within 1km
HealthcareHospital 411m away · 8 clinics within 1km · Pharmacy within 1km
LifestyleNo parks within 2km · 9 restaurants and cafes within 1km
ShoppingSupermarket 1.4km away · Mall 1.0km away · Convenience store within 1km
Getting around
Expressway 1.6 km · Kamarajar SalaiPrimary road 419 m · South Veli StreetRailway line 85 mRailway station 2.2km away (Madurai East)Bus stop within 1km
Water & environment
Canal 669 mWater body 1.3 km · Potramarai Kulam
distances only — not a flood assessment
04

Government Guidance Rate

Tamil Nadu registration department

In Tamil Nadu it’s called the guideline value.

No government guidance rate is shown for this project.

Tamil Nadu publishes street-level guideline values; its full schedule isn't in Horizon's record yet.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

TNRERA · Approved building plan

Town & Country Planning (DTCP)

Town & Country Planning (DTCP)
Planning Permissionapproved 30 Sep 2024 · 2 yrs ago

The promised possession date (14 Mar 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Town & Country Planning (DTCP)

Town & country planning

Has approved 756 RERA projectsabout 1 in 5 in Tamil Nadu.

Builders
467
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by TNRERA

07

Other projects nearby

The register · within 25 km

24 residential and mixed-use projects still under way within 25 km. Step out ring by ring:

Of the 16 projects the radar draws within 6 km — every kind, every stage — 14 are residential and mixed-use projects still under way. This list keeps only those, and looks further out.

3 projects between 1 and 3 km — showing the nearest 3.

1.5 km away

Quality Towers

QUALITY PROMOTERS AND BUILDERS

Jul 2025registered
May 2028target completion
AuthorityTNRERA
1.7 km away

MADHYAPURI

Visvas Promoters Private Limited

Apr 2024registered
Mar 2029target completion
AuthorityTNRERA
2.0 km away

SAI RAM

GD Foundations

Jan 2026registered
Dec 2027target completion
AuthorityTNRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — TNRERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — TNRERA does not publish a complaints register. This read cannot speak to them either way.
  • Escrow — TNRERA does not publish escrow declarations. Whether buyer money is ring-fenced cannot be read here.