Complete project overview

MahaRERA · Registration filing
Plots
892 plots
Land area
1,66,669 sq m
Recreational open space
31,748 sq m

Timeline

RERA registeredOct 2024
Proposed completionDec 2034
TodayJul 2026
Construction progress
Water Supply0%
Landscaping & Tree…0%
Street Lighting0%
Sewerage (Chamber,…2%
Electrical meter r…10%
Storm Water Drains25%
Aggregate area of …40%
Internal Roads & F…45%
Water conservation…50%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

SANDEEP DWELLERS PVT. LTD.

CompanyPromoter type
Nagpur, MAHARASHTRABased in
26Projects
4Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
1,186 homes · 1,497 plotson the public record across 26 projects
1,22,436 sq mbuilt-up filed
2,78,862 sq mplotted area
3,56,237 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Nagpur Improvement Trust9 of 18 projects
Nagpur Municipal CorporationMunicipal Corporation4 of 18 projects
Nagpur Metropolitan Region Development AuthorityMetropolitan Development Authority3 of 18 projects
Nagar Panchayat Besa PiplaMunicipal Council1 of 18 projects
Town Planning & Valuation Department, Assistant Director Of Town Planning, Chandrapurthis project1 of 18 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Chincholi BK
Taluka
Brahmapuri
District
Chandrapur
Pincode
441206
Survey no.
144 188 189 209 211 212 213 216 217 218 220 221 222 223 224 225 226 227 208-1 208-2 and 78 79 80 81 82 83 84 85 86 87 88 89 90 103 104 105 107 108
North boundary
State Highway
East boundary
FSR No 187 190 191 199 206 207 210 of MouzaHardoli
South boundary
Railway Line
West boundary
15 Mtr Road
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 2.9km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 437 mRailway line 1.4 kmRailway station 695m away (Chicholi Buzurg)Limited bus connectivity nearby
Water & environment
Water body 1.3 kmCanal 2.3 kmRiver 2.9 km · Wainganga
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Town Planning & Valuation Department, Assistant Director Of Town Planning, Chandrapur

Layout Permit
Survey no. 144 188 189 209 211 212 213 216 217 218 220 221 222 223 224 225 226 227 208-1 208-2 and 78 79 80 81 82 83 84 85 86 87 88 89 90 103 104 105 107 108
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

The planning authority

The body that sanctioned this project. It has approved 4,607 RERA projects across 33 districts about 1 in 4 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.