HORIZONMarkets
Registration lapsed

This project’s MahaRERA registration has lapsed— it expired and was not renewed. A lapsed project may be stalled, finished-but-not-updated, or abandoned; the record stops here and RERA’s ongoing protections may no longer apply. Confirm the current status directly with MahaRERA before you rely on anything below.

01

Complete project overview

MahaRERA · Registration filing
Floors
5
Buildings
2
Parking
42 spaces
Land area
855 sq m
Sanctioned built-up
1,559 sq m

Timeline

RERA registeredApr 2021
Proposed completionJan 2026
TodayJul 2026
02

Builder’s track record

MahaRERA · Promoter registration

S S DEVELOPERS

PartnershipPromoter type
Pune, MAHARASHTRABased in
17Projects
11Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
380 homes · 59 plotson the public record across 17 projects
56,565 sq mbuilt-up filed
1,32,229 sq mplotted area
1,66,164 sq mland declared
₹203.54 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Nashik Municipal CorporationMunicipal Corporation2 of 9 projects
Ahmedabad Urban Development AuthorityUrban Development Authority1 of 9 projects
Asansol Municipal CorporationMunicipal Corporation1 of 9 projects
Assistant Director Of Town Planning Br Punethis project1 of 9 projects
BIAPPA - Bangalore Airport Area Planning AuthorityUrban Development Authority1 of 9 projects
IndoreTown & Country Planning (DTCP)1 of 9 projects
Pimpri Chinchwad Municipal CorporationMunicipal Corporation1 of 9 projects
Vilas J Yele1 of 9 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Loni-kalbhor
Taluka
Haveli
District
Pune
Pincode
412201
Survey no.
CTS NO. 1231
North boundary
ADJ S NO 656
East boundary
APPROACH ROAD
South boundary
ADJ CTS NO 1230 1229 1228 1227
West boundary
ADJ S NO 657 AND LANE
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 3.0km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 2.9 km · Solapur RoadRailway line 869 m · Pune - Miraj Railway LineRailway station 1.8km away (Phursungi)Limited bus connectivity nearby
Water & environment
Canal 35 mWater body 816 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Assistant Director Of Town Planning Br Pune

Building Permit
Survey no. CTS NO. 1231

The promised possession date (31 Jan 2026) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

The planning authority

The body that sanctioned this project. It has approved 4,607 RERA projects across 33 districts about 1 in 4 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
EncumbranceDeclared financial encumbrance on the project
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.