TIRUPATI ETERNIA GREENS

P52100051439 · MahaRERA · https://gethorizon.in/projects/tirupati-eternia-greens-charholi-haveli-qfqq50h3

01

Complete project overview

MahaRERA · Registration filing
Units
198 units
Floors
9
Buildings
6
Parking
198 spaces
Land area
3,900 sq m
Sanctioned built-up
6,313 sq m

Timeline

RERA registeredJun 2023
Proposed completionDec 2026
TodaySep 2026
Construction progress
Podiums0%
Internal Roads & F…0%
Street Lighting0%
Community Building…0%
Open Parking0%
Water Supply55%
Sewerage (Chamber,…80%
Landscaping & Tree…80%
Water conservation…90%
Energy managemcnt90%
Excavation100%
Basement (if any)100%
Plinth100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
OC-readiness100%
Storm Water Drains100%
Treatment And Disp…100%
Solid Waste Manage…100%
Fire protection an…100%
Electrical meter r…100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Builder registration

S S DEVELOPERS

PartnershipPromoter type
Pune, MAHARASHTRABased in
18Projects
12Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
971 homes · 836 plotson the public record across 18 projects
56,565 sq mbuilt-up filed
2,82,215 sq mplotted area
3,16,150 sq mland declared
₹278.40 Crdeclared build cost

Build cost is what the builder declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Nashik Municipal CorporationMunicipal Corporation2 of 10 projects
Ahmedabad Urban Development AuthorityUrban Development Authority1 of 10 projects
Asansol Municipal CorporationMunicipal Corporation1 of 10 projects
Assistant Director Of Town Planning Br Pune1 of 10 projects
BIAPPA - Bangalore Airport Area Planning AuthorityUrban Development Authority1 of 10 projects
COLLECTOR OFFICE, SIKARGovernment / Local body1 of 10 projects
IndoreTown & Country Planning (DTCP)1 of 10 projects
Pimpri Chinchwad Municipal CorporationMunicipal Corporation1 of 10 projects
Vilas J Yelethis project1 of 10 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from S S DEVELOPERS— the full portfolio →

03

Location

MahaRERA · Registration filing
Village
CHARHOLI
Taluka
Haveli
District
Pune
Pincode
412105
Survey no.
175/1
North boundary
30 METER WIDE ROAD
East boundary
BY PROPERTY OF NILESH MOHAN BURDE ANDOTHERS
South boundary
BY PROPERTY OF BHIKAJI BABAN BURDE AND OTHERS
West boundary
BY PROPERTY OF DYNESHWAR POPAT BURDE AND OTHERS
What’s nearby
Schools1 school within 500m · 11 educational institutions within 1km · College or university 916m away
HealthcareHospital 145m away · 19 clinics within 1km · Doctor's clinic within 1km
LifestylePark 566m away · Gym or sports centre 736m away · 18+ restaurants and cafes within 1km
ShoppingSupermarket 899m away · Convenience store within 1km · Bank 289m away
Getting around
Expressway 75 m · Shivaji RoadPrimary road 856 m · Kamgar PutalaRailway line 783 mMetro station 321m away (Kasba Peth)13 bus stops within 500m
Water & environment
Water body 139 m
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra IGR — Annual Statement of Rates

In Maharashtra it’s called the ready reckoner rate.

₹49,616per sq yd
₹59,340per sq m
Which rate
residential flat (built)
Matched to
The rate published for the village of “CHARHOLI”.
In force
2026-2027 schedule
Spread
₹35,719₹49,616 per sq yd across the places it was taken over

What this number is — and isn’t

  • The minimum value Maharashtra’s registration department will register a sale at. Stamp duty is usually charged on this or the price in the sale deed, whichever is higher.
  • Not a market price. Sales normally register above it, and how far above varies by place and by project.
  • Its fit depends on the grain the state publishes at. This one is matched at the level of village, and says so above. How Horizon decides what to show.
05

Planning authority

MahaRERA · Approved building plan

Vilas J Yele

Building Permit
Survey no. 175/1
The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

The planning authority

The body that approved this project. It has approved 4,607 RERA projects across 33 districts about 1 in 4 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

07

Other projects nearby

The register · within 25 km

3,194 residential projects still under way within 25 km. Step out ring by ring:

Of the 1,827 projects the radar draws within 6 km — every kind, every stage — 645 are residential projects still under way. This list keeps only those, and looks further out.

63 projects within 1 km — showing the nearest 6.

10 m awayResidential / Group Housing

VISION EXOTICA PHASE-II

VISION AVIS GROUPS · Bhosari · Haveli

Feb 2022registered
Dec 2026target completion
Government Guidance Rate₹41,280/sq ydScale168 flatsAuthorityMahaRERA
10 m awayResidential / Group Housing

KOOL HOMES SOLITAIRE PHASE II

REPTON PROPERTIES PRIVATE LIMITED · kondhwa khurd · Haveli

Nov 2021registered
Jun 2027target completion
Government Guidance Rate₹55,026/sq ydScale34 flatsAuthorityMahaRERA
10 m awayResidential / Group Housing

EQUA

AMCO LANDMARK REALTY · WAGHOLI · Haveli

Dec 2021registered
Dec 2026target completion
1 open complaintGovernment Guidance Rate₹50,786/sq ydAuthorityMahaRERA
10 m awayResidential / Group Housing

THE CENTRAL PARK PHASE - III

R RETAIL VENTURES PRIVATE LIMITED · Pimpri Chinchawad · Haveli

Dec 2021registered
Jun 2027target completion
Government Guidance Rate₹58,077/sq ydScale161 flatsAuthorityMahaRERA
10 m awayResidential / Group Housing

Majestique Rhythm County Phase III

MAJESTIQUE RISINGSUN LLP · OUATADE HANDEWADI · Haveli

Jan 2022registered
Dec 2026target completion
Government Guidance Rate₹44,833/sq ydScale270 flatsAuthorityMahaRERA
10 m awayResidential / Group Housing

Radhika Radiance

Shree Samarth Buildcom And Infra · Dattagad Nagar

Apr 2023registered
Dec 2026target completion
AuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.