17 on filequarterly progress reports filed with RERA
Timeline
RERA registeredOct 2021
Proposed completionAug 2026
TodaySep 2026
Construction progress
100% overall, as filed
Internal Roads And Footpaths100%
Water Supply100%
Sewerage100%
Storm Water Drains100%
Landscaping And Tree Planting100%
Street Lighting100%
Open Parking100%
Community Buildings100%
Treatment And Disposal Of Sewerage And Sullage Wat100%
Solid Waste Management And Disposal100%
Water Conservation Rain Water Harvesting100%
Energy Maanagement100%
Boundary Wall100%
Security Service100%
Gym100%
Place Of Worship100%
Swimming Pool100%
Club House100%
Children Play Area100%
From the builder's latest quarterly progress report filed with RERA Chhattisgarh — % complete overall and per infrastructure work, as of that filing. A dated snapshot, not a live tracker.
Find your flat
Filed by type and size, in the batches the builder registered — not a per-flat listing. Look yours up.
131 units across 15 batches
TypeArea sq mCount
3BHK1241
3BHK1241
3BHK1351
4BHK15715
4BHK1371
4BHK17217
3BHK12915
3BHK11813
3BHK11513
3BHK11413
3BHK10514
3BHK10814
Commercial306
Commercial266
3bk1291
Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).
Build cost is what the builder declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.
Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
Expressway 672 mPrimary road 2.3 km · Raipur BypassRailway line 2.4 kmRailway station 5.0km away (Telibandha)Limited bus connectivity nearby
Water & environment
Water body 197 mCanal 1.7 km · Naala
distances only — not a flood assessment
Land, title & encumbrance
Mortgage14 unit(s) declared under mortgage to a bank/lender for project finance
As declared by the builder at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
Price analysisdeclared build cost — not a sale price
₹80.43 Cr declared to build 133 flats. What that works out to:
₹60.47 Lakhdeclared cost per flatall-in — land + construction
27%of the cost is land
This is what the builder filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.
Location & price analysis — done
04
Government Guidance Rate
Chhattisgarh registration department
In Chhattisgarh it’s called the collector guideline rate.
No government guidance rate is shown for this project.
Chhattisgarh's government guidance rates aren't in Horizon's record yet.
That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.
Government Guidance Rate — done
05
Complaints & litigation
RERA Chhattisgarh · public record
Complaints, as the builder reports them
None in the builder’s latest quarterly return to RERA Chhattisgarh.
The builder’s own count of grievances it received — not RERA Chhattisgarh’s register, which isn’t published. Cases the builder declares are listed below.
What the builder declared
Declared to RERA Chhattisgarh
Litigation
None declared in this filing
Only what the builder declared, or what RERA Chhattisgarh records itself, can appear here — a case filed elsewhere and never declared would not.
Not a verdict. A complaint can be dismissed and a case can be won; an order can be appealed.
Not a clean bill. An empty record means nothing was filed with RERA Chhattisgarh, or that this register doesn’t publish it — never that nothing happened.
Complaints & litigation — done
06
Other projects nearby
The register · within 25 km
156 residential projects still under way within 25 km. Step out ring by ring:
Of the 401 projects the radar draws within 6 km — every kind, every stage — 82 are residential projects still under way. This list keeps only those, and looks further out.
7 projects within 1 km — showing the nearest 6.
250 m awayGroup Housing
THE PARKSYDE PHASE - II
RISHABH BUILDTECH INDIA PRIVATE LIMITED · Raipur
8 yr
Sep 2018registered
Sep 2026target completion
⚠ 8 open complaintsDeclared cost₹67.34 CrScale182 flatsAuthorityRERA Chhattisgarh