Complete project overview

K-RERA · Registration filing
Units
75 units
Mix
45 × 3BHK · 30 × 2BHK
Booked
67 of 75 filed sold/bookedas declared in the RERA filing
Buildings
2
Land area
2,900 sq m
Floor area
14,754 sq m
Description
THE MAPLE BAY BY FAVOURITE HOMES

Timeline

RERA registeredFeb 2022
Project startedFeb 2022
Proposed completionJun 2025
TodayJul 2026
Construction progress

87% overall, as filed

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation100%
Basement(s) and Plinth100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Installation of lifts, water pumps etc100%
Fire Fighting Fittings and Equipment100%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc100%
Excavation100%
Basement(s) and Plinth100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Installation of lifts, water pumps etc100%
Fire Fighting Fittings and Equipment100%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc100%
Per-activity completion % from the promoter's construction-task checklist filed with K-RERA — overall is the average across activities, as of that filing. A dated snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

8 of 75 available
TypeArea sq mAvailable
3BHK1180 of 15
2BHK786 of 15
3BHK1000 of 15
2BHK761 of 15
3BHK1051 of 15

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system.

02

Builder’s track record

K-RERA · Promoter registration

FAVOURITE CONSTRUCTIONS PRIVATE LIMITED

CompanyPromoter type
Thiruvananthapuram, KeralaBased in
Yes — the promoter declared prior project experienceDeclared prior experience
28Projects
1Cities
2021–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
1,600 homes · 135 plotson the public record across 28 projects
3,01,646 sq mbuilt-up filed
47,835 sq mplotted area
1,07,423 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Thiruvananthapuram Municipal CorporationMunicipal Corporationthis project19 of 27 projects
Kadinamkulam Grama PanchayatGrama Panchayat2 of 27 projects
Andoorkonam Grama Panchayat ThiruvananthapuramLocal body (LSGI)1 of 27 projects
Andoorkonam Grama Panchayat TrivandrumLocal body (LSGI)1 of 27 projects
Manickal Grama PanchayatGrama Panchayat1 of 27 projects
Manikkal Grama PanchayatGrama Panchayat1 of 27 projects
Thiiruvananthapuram Municipal CorporationMunicipal Corporation1 of 27 projects
Thiruvananthpuram Municipal CorporationMunicipal Corporation1 of 27 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

K-RERA · Registration filing
Street
MANNANTHALA- PEROORKADA ROAD
Village
ULOOR
Taluk
THIRUVANANTHAPRUAM
District
Thiruvananthapuram
Pincode
695015
Survey no.
67/7 AND 67/7-1
Patta no.
33984 AND 33985
What’s nearby
Schools1 school within 500m · 5 educational institutions within 1km · College or university 280m away
HealthcareHospital 58m away · 1 clinic within 1km
Lifestyle1 park within 500m · Gym or sports centre 1.9km away · 19+ restaurants and cafes within 1km
ShoppingSupermarket 67m away · Mall 90m away · Convenience store within 500m
Getting around
Primary road 10 m · Thiruvanathapuram - Thenmala RoadNo metro or railway within 5km12 bus stops within 500m
Water & environment
Water body 318 m · Aduppu Kootan ParaRiver 1.2 km · Killi
distances only — not a flood assessment
04

Planning authority

K-RERA · Approved building plan

Thiruvananthapuram Municipal Corporation

Municipal Corporation
approved 2 Feb 2022 · 4 yrs ago
Building Permit no. UE1/BA/01/2022 (UE1/351/2022)Survey no. 67/7 AND 67/7-1

The promised possession date (30 Jun 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan UE1/BA/01/2022 (UE1/351/2022) on the approving authority’s portal to confirm the sanction.

The approving body, at scale

Thiruvananthapuram Municipal Corporation

Municipal corporation / municipality

Has approved 224 RERA projectsabout 1 in 7 in Kerala, more than any other body in the state.

an apartments market91% apartments · 9% plotted layouts. Apartments like yours are this body's core business.

Builders
90
On record
12,045 flats · 635 plots
Since
2021

More apartment-heavy than Kerala overall — 91% apartments here vs 81% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — K-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — K-RERA does not publish a complaints register. This read cannot speak to them either way.