45 of 62 filed sold/bookedas declared in the RERA filing
Buildings
1
Land area
2,065 sq m
Floor area
11,226 sq m
Description
Urbanscape Solitaire
Timeline
Project startedNov 2022
RERA registeredNov 2022
Proposed completionNov 2026
TodaySep 2026
Construction progress
37% overall, as filed
Completion of terraces floor each building0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Sanitary Fittings5%
Electrical Fittings5%
Installation of lifts, water pumps etc10%
Fire Fighting Fittings and Equipment10%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc10%
The external plumbing and external plastering30%
Overhead and Underground Water Tanks.45%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings50%
Staircases, Lifts Wells90%
Excavation100%
Basement(s) and Plinth100%
Slabs of Super Structure100%
Per-activity completion % from the builder's construction-task checklist filed with K-RERA — overall is the average across activities, as of that filing. A dated snapshot, not a live tracker.
Find your flat
Filed by type and size, in the batches the builder registered — not a per-flat listing. Look yours up.
17 of 62 available
TypeArea sq mAvailable
2BHK824 of 15
3BHK1530 of 1
3BHK1074 of 15
3BHK1064 of 15
3BHK1760 of 1
2BHK825 of 15
Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the builder declared — not a live booking system.
Complete project overview — done
02
Builder’s track record
K-RERA · Builder registration
Urbanscape Properties LLP
Limited Liability PartnershipPromoter type
Thiruvananthapuram, KeralaBased in
Yes — the promoter declared prior project experienceDeclared prior experience
325 homes · 30 plotson the public record across 7 projects
60,289 sq mbuilt-up filed
9,751 sq mplotted area
21,263 sq mland declared
These are sums of what the builder has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.
Planning authoritiesthis builder's portfolio, by approving body
Thiruvananthapuram Municipal CorporationMunicipal Corporationthis project4 of 7 projects
Manickal Grama PanchayatGrama Panchayat1 of 7 projects
Municipal Corporation ThiruvananthapuramLocal body (LSGI)1 of 7 projects
ThiruvananthapuramLocal body (LSGI)1 of 7 projects
Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.
Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
Primary road 2.7 km · Thiruvanathapuram - Thenmala RoadRailway line 4.9 kmNo metro or railway within 5km4 bus stops within 500m
Water & environment
Water body 249 m · Avastamcode kulamRiver 973 m · Killi
distances only — not a flood assessment
Land, title & encumbrance
Land ownershipBuilt on land that includes third-party owners — a landowner (joint-development) arrangement is declared; confirm the title and your share
As declared by the builder at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
Location — done
04
Government Guidance Rate
Kerala Registration Department — fair value
In Kerala it’s called the fair value.
₹2,759per sq yd
₹3,300per sq m
Which rate
Residential Plot with Corp./Mun./Panch. road access
Matched to
The rate published for the village of “Vattiyurkavu”.
What this number is — and isn’t
The minimum value Kerala’s registration department will register a sale at. Stamp duty is usually charged on this or the price in the sale deed, whichever is higher.
Not a market price. Sales normally register above it, and how far above varies by place and by project.
Its fit depends on the grain the state publishes at. This one is matched at the level of village, and says so above. How Horizon decides what to show.
Government Guidance Rate — done
05
Planning authority
K-RERA · Approved building plan
Thiruvananthapuram Municipal Corporation
Municipal Corporation
approved 5 Nov 2022 · 3 yrs ago
Building Permit no. E8/BA/6177/2022Survey no. 96
The occupancy certificate — the proof that isn’t here
An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.
Verify it yourself — look up plan E8/BA/6177/2022 on the approving authority’s portal to confirm the approval.
The approving body, at scale
Thiruvananthapuram Municipal Corporation
Municipal corporation / municipality
Has approved 224 RERA projects — about 1 in 7 in Kerala, more than any other body in the state.
an apartments market — 91% apartments · 9% plotted layouts. Apartments like yours are this body's core business.
Builders
90
On record
12,045 flats · 635 plots
Since
2021
More apartment-heavy than Kerala overall — 91% apartments here vs 81% statewide.
Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.
The approving body's other projects: counted by Horizon across the register.
06Complaints & litigation
K-RERA's public record lists no complaints or litigation for this project.
07Other projects nearby
The RERA-registered projects Horizon holds within 25 km of these coordinates.
Compiled by Horizon from public records. Each fact is reproduced as its source publishes it, and Horizon does not verify filings on the ground. The live record: gethorizon.in/projects/urbanscape-solitaire-vattiyoorkavu-thiruvananthapuram-6z6bpt3w.
Horizon does not rate, review, score or signal, and it gives no verdict, opinion or forecast. Its only aim is to seek the truth through data: what the public record says, where each fact comes from, and where the record is silent. Nothing in this document is legal, financial or investment advice; what to make of it is yours to decide.