HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
8
Buildings
2
Parking
76 spaces
Land area
1,260 sq m
Sanctioned built-up
3,585 sq m

Timeline

RERA registeredJun 2023
Proposed completionJul 2025
TodayJul 2026
02

Builder’s track record

MahaRERA · Promoter registration

Yash Infra

PartnershipPromoter type
Thane, MAHARASHTRABased in
14Projects
6Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
442 homeson the public record across 14 projects
63,860 sq mbuilt-up filed
21,359 sq mland declared
₹15.00 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Thane Municipal CorporationMunicipal Corporationthis project3 of 11 projects
Ahmedabad Municipal CorporationMunicipal / Corporation2 of 11 projects
Thane Municipal Corporation ThaneMunicipal Corporation2 of 11 projects
Kalyan Dombivli Municipal CorporationMunicipal Corporation1 of 11 projects
Kulgaon Badlapur Municipal CouncilMunicipal Council1 of 11 projects
Mumbai Metropolitan Region Development AuthorityMetropolitan Development Authority1 of 11 projects
Vadodara Municipal CorporationMunicipal / Corporation1 of 11 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Thane (M Corp.)
Taluka
Thane
District
Thane
Pincode
400602
Survey no.
Sector 2 , 108/4C , 108/4D
North boundary
Parimala chs
East boundary
Mohan Mahal chs
South boundary
Ram maruti road
West boundary
Kamal chs
What’s nearby
SchoolsNearest school 1.5km away · Library 886m away
HealthcareHospital 101m away · 2 clinics within 1km
LifestylePark 1.7km away · Gym or sports centre 1.7km away · 4 restaurants and cafes within 1km
ShoppingSupermarket 195m away · Mall 1.3km away · Bank 155m away
Getting around
Expressway 18 m · Thane Ghodbunder RoadPrimary road 236 m · Eastern Express TurnpikeRailway line 1.0 kmMetro station 650m away (Kapurbawdi Station)16 bus stops within 500m
Water & environment
Water body 490 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Thane Municipal Corporation

Municipal Corporation
Building Permit
Survey no. Sector 2 , 108/4C , 108/4D

The promised possession date (31 Jul 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Thane Municipal Corporation

Municipal corporation

Has approved 489 RERA projects2.4% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
318
On record
7,890 flats · 0 plots
Reach
5 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
EncumbranceDeclared financial encumbrance on the project
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.