HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
2
Buildings
2
Parking
48 spaces
Land area
424 sq m
Sanctioned built-up
2,775 sq m
Recreational open space
771 sq m

Timeline

RERA registeredNov 2021
Proposed completionDec 2024
TodayJul 2026
Construction progress
Podiums0%
Superstructure0%
Flat fit-out0%
Internal Roads & F…0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Street Lighting0%
Treatment And Disp…0%
Solid Waste Manage…0%
Water conservation…0%
Energy managemcnt0%
Fire protection an…0%
Aggregate area of …0%
Internal finishes17%
OC-readiness17%
External finishes22%
Stairs & lifts59%
Electrical meter r…60%
Excavation100%
Basement (if any)100%
Plinth100%
Stilt floor100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

SHREE VENKATESH BUILDCON PVT LTD

CompanyPromoter type
Pune, MAHARASHTRABased in
20Projects
2Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
1,074 homeson the public record across 20 projects
2,31,893 sq mbuilt-up filed
73,817 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Pune (M Corp.)
Taluka
Pune City
District
Pune
Pincode
411004
Survey no.
NEW CTS NO 137 OLD 137 138 PART CTS 170 171 AND 172 ERANDWANE
North boundary
CTS NO 139 PART AND 169
East boundary
12 MTR WIDE DP ROAD
South boundary
18 MTR WIDE DP ROAD
West boundary
CTS NO 139 AND 158
What’s nearby
Schools2 schools within 500m · 5 educational institutions within 1km · College or university 1.4km away
HealthcareHospital 304m away · 19 clinics within 1km · Pharmacy within 500m
Lifestyle1 park within 500m · Gym or sports centre 395m away · 64+ restaurants and cafes within 1km
ShoppingSupermarket 808m away · Mall 574m away · Convenience store within 1km
Getting around
Expressway 2.7 km · Chimaji Appa Peshwe PathPrimary road 397 m · Karve RoadRailway line 4.0 km · Mumbai–Pune RailwayMetro station 482m away (SNDT College)4 bus stops within 500m
Water & environment
Water body 637 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Pune Municipal Corporation

Municipal Corporation
Building Permit
Survey no. NEW CTS NO 137 OLD 137 138 PART CTS 170 171 AND 172 ERANDWANE

The promised possession date (31 Dec 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Pune Municipal Corporation

Municipal corporation

Has approved 1,863 RERA projectsabout 1 in 11 in Maharashtra.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,351
On record
9,749 flats · 439 plots
Reach
3 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.