HORIZONMarkets
01

Complete project overview

K-RERA · Registration filing
Units
82 units
Mix
54 × 3BHK · 28 × 2BHK
Booked
82 of 82 filed sold/bookedas declared in the RERA filing
Buildings
1
Land area
3,278 sq m
Floor area
15,154 sq m
Description
ASSET CHAMBER

Timeline

RERA registeredMay 2021
Project startedJun 2021
Proposed completionJun 2025
TodayJul 2026
Construction progress

39% overall, as filed

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
The external plumbing and external plastering20%
Completion of terraces floor each building20%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc26%
Electrical Fittings28%
Sanitary Fittings30%
Installation of lifts, water pumps etc30%
Fire Fighting Fittings and Equipment33%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings35%
Overhead and Underground Water Tanks.35%
Staircases, Lifts Wells36%
Slabs of Super Structure53%
Stilt Floor82%
Excavation100%
Basement(s) and Plinth100%
Per-activity completion % from the promoter's construction-task checklist filed with K-RERA — overall is the average across activities, as of that filing. A dated snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

0 of 82 available
TypeArea sq mAvailable
3BHK1050 of 26
2BHK760 of 28
3BHK1110 of 28

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system.

02

Builder’s track record

K-RERA · Promoter registration

ASSET HOMES PRIVATE LIMITED

CompanyPromoter type
Kannur, KeralaBased in
Yes — the promoter declared prior project experienceDeclared prior experience
57Projects
1Cities
2021–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
3,706 homeson the public record across 57 projects
6,15,597 sq mbuilt-up filed
1,59,715 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Kochi Municipal CorporationMunicipal Corporation6 of 55 projects
Kannur Municipal CorporationMunicipal Corporationthis project5 of 55 projects
Thrissur Municipal CorporationMunicipal Corporation5 of 55 projects
Thrikkakara MunicipalityMunicipality4 of 55 projects
Kozhikode Municipal CorporationMunicipal Corporation3 of 55 projects
Thiruvananthapuram Municipal CorporationMunicipal Corporation3 of 55 projects
Kottayam MunicipalityMunicipality2 of 55 projects
Thrikakkara MunicipalityMunicipality2 of 55 projects
Thrikkakara Municipality ErnakulamLocal body (LSGI)2 of 55 projects
Alappuzha MuncipalityLocal body (LSGI)1 of 55 projects
Chengamanad Grama PanchayatGrama Panchayat1 of 55 projects
Cheranallur Grama PanchayatGrama Panchayat1 of 55 projects
Cochin Municipal CorporationMunicipal Corporation1 of 55 projects
Ettumanoor MunicipalityMunicipality1 of 55 projects
Kizhakkambalam Grama Panchayat ErnakulamLocal body (LSGI)1 of 55 projects
Kochi Municipal Corporation ErnakulamLocal body (LSGI)1 of 55 projects
Kollam Municipal CorporationMunicipal Corporation1 of 55 projects
Kozhikode Municipal Corporation KozhikodeLocal body (LSGI)1 of 55 projects
Maradu MunicipalityMunicipality1 of 55 projects
Mulakunnathukavu Grama Panchayat ThrissurLocal body (LSGI)1 of 55 projects
Pathanamthitta MunicipalityMunicipality1 of 55 projects
Puthupally Grama PanchayatGrama Panchayat1 of 55 projects
Puthupally PanchayathLocal body (LSGI)1 of 55 projects
Puthuppally Grama PanchayatGrama Panchayat1 of 55 projects
Technopark Area Single Window Clearance BoardLocal body (LSGI)1 of 55 projects
Thiruvananthapuram Muncipal Municipal CorporationMunicipal Corporation1 of 55 projects
Thiruvanathapuram Municipal CorporationMunicipal Corporation1 of 55 projects
Thrikkakara MunicipaltyLocal body (LSGI)1 of 55 projects
Thrikkakkara MunicipalityMunicipality1 of 55 projects
Thrissur CoporationLocal body (LSGI)1 of 55 projects
Tripunithura MunicipalityMunicipality1 of 55 projects
Trivandrum Municipal CorporationMunicipal Corporation1 of 55 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

K-RERA · Registration filing
Street
CHOVVA
Village
ELAYAVOOR
Taluk
Kannur
District
Kannur
Pincode
670001
Survey no.
75/133,75/108
Patta no.
10479,8044
What’s nearby
Schools5 schools within 1km · 7 educational institutions within 1km · Library 357m away
HealthcareHospital 1.4km away · Clinic within 2km
LifestyleNo parks within 2km
ShoppingSupermarket 698m away · Mall 1.1km away · Convenience store within 500m
Getting around
Expressway 568 m · Kannur-Calicut-Valanchery HighwayPrimary road 1.4 km · Kannur-Calicut-Valanchery HighwayRailway line 1.0 kmRailway station 1.0km away (Kannur South)3 bus stops within 500m
Water & environment
Water body 684 mCanal 735 m · pazassi canalRiver 939 m · Kaanaam River
distances only — not a flood assessment
Land, title & encumbrance
Land ownershipBuilt on land that includes third-party owners — a landowner (joint-development) arrangement is declared; confirm the title and your share
As declared by the promoter at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
04

Planning authority

K-RERA · Approved building plan

Kannur Municipal Corporation

Municipal Corporation
approved 31 Mar 2021 · 5 yrs ago
Building Permit no. EZ BA 135/20-21Survey no. 75/133,75/108

The promised possession date (30 Jun 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan EZ BA 135/20-21 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

Kannur Municipal Corporation

Municipal corporation / municipality

Has approved 17 RERA projects1.1% of Kerala.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
7
On record
1,169 flats · 0 plots
Since
2021

More apartment-heavy than Kerala overall — 100% apartments here vs 81% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — K-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — K-RERA does not publish a complaints register. This read cannot speak to them either way.