HORIZONMarkets
01

Complete project overview

K-RERA · Registration filing
Units
45 units
Mix
26 × 2BHK · 19 × 3BHK
Booked
45 of 45 filed sold/bookedas declared in the RERA filing
Buildings
1
Land area
1,928 sq m
Floor area
9,567 sq m
Description
ASSET GALLERIA

Timeline

Project startedJan 2018
RERA registeredJun 2021
Proposed completionOct 2023
TodayJul 2026
Construction progress

88% overall, as filed

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Installation of lifts, water pumps etc100%
Fire Fighting Fittings and Equipment100%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc100%
Per-activity completion % from the promoter's construction-task checklist filed with K-RERA — overall is the average across activities, as of that filing. A dated snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

0 of 45 available
TypeArea sq mAvailable
2BHK720 of 9
3BHK1340 of 1
2BHK680 of 8
3BHK1010 of 9
3BHK980 of 9
2BHK650 of 9

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system.

02

Builder’s track record

K-RERA · Promoter registration

ASSET HOMES PRIVATE LIMITED

CompanyPromoter type
Thrissur, KeralaBased in
Yes — the promoter declared prior project experienceDeclared prior experience
57Projects
1Cities
2021–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
3,706 homeson the public record across 57 projects
6,15,597 sq mbuilt-up filed
1,59,715 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Kochi Municipal CorporationMunicipal Corporation6 of 55 projects
Kannur Municipal CorporationMunicipal Corporation5 of 55 projects
Thrissur Municipal CorporationMunicipal Corporationthis project5 of 55 projects
Thrikkakara MunicipalityMunicipality4 of 55 projects
Kozhikode Municipal CorporationMunicipal Corporation3 of 55 projects
Thiruvananthapuram Municipal CorporationMunicipal Corporation3 of 55 projects
Kottayam MunicipalityMunicipality2 of 55 projects
Thrikakkara MunicipalityMunicipality2 of 55 projects
Thrikkakara Municipality ErnakulamLocal body (LSGI)2 of 55 projects
Alappuzha MuncipalityLocal body (LSGI)1 of 55 projects
Chengamanad Grama PanchayatGrama Panchayat1 of 55 projects
Cheranallur Grama PanchayatGrama Panchayat1 of 55 projects
Cochin Municipal CorporationMunicipal Corporation1 of 55 projects
Ettumanoor MunicipalityMunicipality1 of 55 projects
Kizhakkambalam Grama Panchayat ErnakulamLocal body (LSGI)1 of 55 projects
Kochi Municipal Corporation ErnakulamLocal body (LSGI)1 of 55 projects
Kollam Municipal CorporationMunicipal Corporation1 of 55 projects
Kozhikode Municipal Corporation KozhikodeLocal body (LSGI)1 of 55 projects
Maradu MunicipalityMunicipality1 of 55 projects
Mulakunnathukavu Grama Panchayat ThrissurLocal body (LSGI)1 of 55 projects
Pathanamthitta MunicipalityMunicipality1 of 55 projects
Puthupally Grama PanchayatGrama Panchayat1 of 55 projects
Puthupally PanchayathLocal body (LSGI)1 of 55 projects
Puthuppally Grama PanchayatGrama Panchayat1 of 55 projects
Technopark Area Single Window Clearance BoardLocal body (LSGI)1 of 55 projects
Thiruvananthapuram Muncipal Municipal CorporationMunicipal Corporation1 of 55 projects
Thiruvanathapuram Municipal CorporationMunicipal Corporation1 of 55 projects
Thrikkakara MunicipaltyLocal body (LSGI)1 of 55 projects
Thrikkakkara MunicipalityMunicipality1 of 55 projects
Thrissur CoporationLocal body (LSGI)1 of 55 projects
Tripunithura MunicipalityMunicipality1 of 55 projects
Trivandrum Municipal CorporationMunicipal Corporation1 of 55 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

K-RERA · Registration filing
Street
THRISSUR-SHORANUR ROAD
Village
THRISSUR
Taluk
Thrissur
District
Thrissur
Pincode
680020
Survey no.
3162PT2, 191/1/1, 191/2/1, 192/2/1, 192/1/2, 192/2, 192/3/1, 191/1/2, 192/1/1, 192/2/2 and 3162/PT1
Patta no.
13134
What’s nearby
Schools6 schools within 1km · 12 educational institutions within 1km · College or university 247m away
HealthcareHospital 280m away · 7 clinics within 1km · Pharmacy within 1km
LifestylePark 872m away · Playground within 500m · Gym or sports centre 410m away
ShoppingSupermarket 73m away · Mall 361m away · Convenience store within 500m
Getting around
Expressway 4.8 km · Salem - Kochi - Kanyakumari HighwayPrimary road 5 m · Thrissur-Shornur RoadRailway line 795 mRailway station 754m away (Punkunnam)5 bus stops within 500m
Water & environment
Water body 132 m · Vadakke Chira
distances only — not a flood assessment
Land, title & encumbrance
Land ownershipBuilt on land that includes third-party owners — a landowner (joint-development) arrangement is declared; confirm the title and your share
As declared by the promoter at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
04

Planning authority

K-RERA · Approved building plan

Thrissur Municipal Corporation

Municipal Corporation
approved 9 Jan 2018 · 8 yrs ago
Building Permit no. DW3/BA/371/16-17Survey no. 3162PT2, 191/1/1, 191/2/1, 192/2/1, 192/1/2, 192/2, 192/3/1, 191/1/2, 192/1/1, 192/2/2 and 3162/PT1

The promised possession date (30 Oct 2023) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan DW3/BA/371/16-17 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

Thrissur Municipal Corporation

Municipal corporation / municipality

Has approved 91 RERA projectsabout 1 in 17 in Kerala.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
51
On record
5,515 flats · 15 plots
Since
2021

More apartment-heavy than Kerala overall — 99% apartments here vs 81% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — K-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — K-RERA does not publish a complaints register. This read cannot speak to them either way.