Complete project overview

MahaRERA · Registration filing
Plots
90 plots
Land area
34,836 sq m

Timeline

RERA registeredJan 2025
Proposed completionDec 2030
TodayJul 2026
Construction progress
Water Supply0%
Water conservation…0%
Electrical meter r…0%
Internal Roads & F…40%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

INDU DEVELOPERS

PartnershipPromoter type
Thane, MAHARASHTRABased in
2Projects
1City
2019–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
10 homes · 90 plotson the public record across 2 projects
1,445 sq mbuilt-up filed
34,836 sq mplotted area
35,337 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Greater Hyderabad Municipal Corporation (GHMC)Municipal / Corporation1 of 2 projects
Office Of The District Collector And District Magistrate, Raigad–AlibagCollector officethis project1 of 2 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Boriwali
Taluka
Karjat
District
Raigarh
Pincode
410201
Survey no.
81/1, 81/2, 81/3 and 81/4
North boundary
Survey No 67
East boundary
15 Mtr Road
South boundary
Existing O D R Road
West boundary
Survey No 53
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 2.1km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 2.2 kmPrimary road 1.0 kmNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
River 702 m · Shilhar NadiWater body 3.9 km
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Office Of The District Collector And District Magistrate, Raigad–Alibag

Collector office
Layout Permit
Survey no. 81/1, 81/2, 81/3 and 81/4
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

The planning authority

The body that sanctioned this project. It has approved 4,607 RERA projects across 33 districts about 1 in 4 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.