HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
8
Parking
48 spaces
Land area
480 sq m
Sanctioned built-up
1,949 sq m

Timeline

RERA registeredDec 2024
Proposed completionNov 2026
TodayJul 2026
Construction progress
Excavation0%
Basement (if any)0%
Podiums0%
Plinth0%
Stilt floor0%
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Treatment And Disp…0%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

SHREE INFRA

PartnershipPromoter type
Thane, MAHARASHTRABased in
27Projects
11Cities
2018–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
2,245 homeson the public record across 27 projects
2,55,409 sq mbuilt-up filed
1,00,966 sq mland declared
₹354.29 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Vadodara Municipal CorporationMunicipal / Corporation7 of 25 projects
Surat Municipal CorporationMunicipal / Corporation4 of 25 projects
Others3 of 25 projects
Ahmedabad Urban Development AuthorityUrban Development Authority2 of 25 projects
Rajkot Municipal CorporationMunicipal / Corporation2 of 25 projects
Surat Urban Development AuthorityUrban Development Authority2 of 25 projects
Ahmedabad Municipal CorporationMunicipal / Corporation1 of 25 projects
Chikhali Municipal CouncilMunicipal Council1 of 25 projects
Commissioner, ULBMunicipal / Corporation1 of 25 projects
Greater Hyderabad Municipal Corporation (GHMC)Municipal / Corporation1 of 25 projects
Kulgoan Badlapur Municipal CouncilMunicipal Council1 of 25 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Thane (M Corp.)
Taluka
Thane
District
Thane
Pincode
400601
Survey no.
TIKKA NO 13, CTS NO 378
North boundary
GANESH DARSHAN CHS
East boundary
D ALMEIDA CHS
South boundary
SANDIP CHS
West boundary
JAI JAGDABA CHS
What’s nearby
SchoolsNearest school 1.1km away · College or university 1.1km away · Library 762m away
HealthcareHospital 205m away · 14 clinics within 1km · Pharmacy within 500m
LifestylePark 576m away · Gym or sports centre 1.3km away · 18+ restaurants and cafes within 1km
ShoppingSupermarket 954m away · Mall 1.3km away · Bank 280m away
Getting around
Expressway 981 mPrimary road 297 m · Lal Bahadur Shastri MargRailway line 1.2 kmRailway station 1.2km away (Thane)16 bus stops within 500m
Water & environment
Water body 290 m
distances only — not a flood assessment
Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.