Complete project overview

MahaRERA · Registration filing
Floors
8
Buildings
4
Parking
111 spaces
Land area
1,282 sq m
Sanctioned built-up
4,033 sq m

Timeline

RERA registeredJun 2025
Proposed completionDec 2030
TodayJul 2026
Construction progress
Excavation0%
Basement (if any)0%
Podiums0%
Plinth0%
Stilt floor0%
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Water Supply0%
Sewerage (Chamber,…0%
Community Building…0%
Water conservation…0%
Open Parking0%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

SHREE INFRA

PartnershipPromoter type
Thane, MAHARASHTRABased in
27Projects
11Cities
2018–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
2,245 homeson the public record across 27 projects
2,55,409 sq mbuilt-up filed
1,00,966 sq mland declared
₹354.29 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Vadodara Municipal CorporationMunicipal / Corporation7 of 25 projects
Surat Municipal CorporationMunicipal / Corporation4 of 25 projects
Others3 of 25 projects
Ahmedabad Urban Development AuthorityUrban Development Authority2 of 25 projects
Rajkot Municipal CorporationMunicipal / Corporation2 of 25 projects
Surat Urban Development AuthorityUrban Development Authority2 of 25 projects
Ahmedabad Municipal CorporationMunicipal / Corporation1 of 25 projects
Chikhali Municipal CouncilMunicipal Council1 of 25 projects
Commissioner, ULBMunicipal / Corporation1 of 25 projects
Greater Hyderabad Municipal Corporation (GHMC)Municipal / Corporation1 of 25 projects
Kulgoan Badlapur Municipal CouncilMunicipal Councilthis project1 of 25 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Badlapur (M Cl)
Taluka
Ambarnath
District
Thane
Pincode
421503
Survey no.
S.N.9A H.N.1/1/9/1Part P.N.1, S.N.10B H.N.2/9Part P.N.8, S.N.10B H.N.2/9Part P.N.9 & S.N.9A H.N.1/1/9/B Part P.N.13
North boundary
D P ROAD 12 M W
East boundary
INTERNAL ROAD 6 M W
South boundary
S N 9 A 1 1 9 B PLOT NO 13
West boundary
SHANTI APARTMENT
What’s nearby
SchoolsNo schools within 2km · Library 924m away
HealthcareHospital 1.1km away · Clinic within 2km
Lifestyle1 park within 500m · 3 restaurants and cafes within 1km
ShoppingNo supermarket within 2km
Getting around
Primary road 303 m · Pipeline RoadRailway line 202 m · Mumbai-Pune RailwayRailway station 1.8km away (Badlapur)Limited bus connectivity nearby
Water & environment
Water body 617 m · Lotus Lake
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Kulgoan Badlapur Municipal Council

Municipal Council
Building Permit
Survey no. S.N.9A H.N.1/1/9/1Part P.N.1, S.N.10B H.N.2/9Part P.N.8, S.N.10B H.N.2/9Part P.N.9 & S.N.9A H.N.1/1/9/B Part P.N.13
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Kulgoan Badlapur Municipal Council

Municipal corporation

Has approved 44 RERA projects0.2% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
40
On record
81 flats · 0 plots
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.