Complete project overview

K-RERA · Registration filing
Units
156 units
Mix
156 × 2BHK
Booked
109 of 156 filed sold/bookedas declared in the RERA filing
Buildings
2
Land area
4,753 sq m
Floor area
15,826 sq m
Description
CONFIDENT AMAZE

Timeline

RERA registeredMar 2024
Project startedApr 2024
Proposed completionApr 2029
TodayJul 2026
Construction progress

16% overall, as filed

Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
Staircases, Lifts Wells0%
Overhead and Underground Water Tanks.0%
The external plumbing and external plastering0%
Completion of terraces floor each building0%
Installation of lifts, water pumps etc0%
Fire Fighting Fittings and Equipment0%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Slabs of Super Structure0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
Staircases, Lifts Wells0%
Overhead and Underground Water Tanks.0%
The external plumbing and external plastering0%
Completion of terraces floor each building0%
Installation of lifts, water pumps etc0%
Fire Fighting Fittings and Equipment0%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Slabs of Super Structure15%
Stilt Floor35%
Basement(s) and Plinth76%
Stilt Floor88%
Excavation100%
Basement(s) and Plinth100%
Excavation100%
Per-activity completion % from the promoter's construction-task checklist filed with K-RERA — overall is the average across activities, as of that filing. A dated snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

47 of 156 available
TypeArea sq mAvailable
2BHK4,55241 of 80
2BHK4,3246 of 76

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system.

02

Builder’s track record

K-RERA · Promoter registration

Confident Projects Residential

PartnershipPromoter type
Thiruvananthapuram, KeralaBased in
Yes — the promoter declared prior project experienceDeclared prior experience
48Projects
1Cities
2021–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
4,766 homes · 21 plotson the public record across 48 projects
5,97,537 sq mbuilt-up filed
16,390 sq mplotted area
1,90,417 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Thiruvananthapuram Municipal CorporationMunicipal Corporation7 of 48 projects
Thrikkakara MunicipalityMunicipality5 of 48 projects
Thrissur Municipal CorporationMunicipal Corporation5 of 48 projects
Kadinamkulam Grama PanchayatGrama Panchayatthis project3 of 48 projects
Kochi Municipal CorporationMunicipal Corporation3 of 48 projects
Kottayam MunicipalityMunicipality3 of 48 projects
Kozhikode Municipal CorporationMunicipal Corporation3 of 48 projects
Andoorkonam PanchayatLocal body (LSGI)1 of 48 projects
Cheranalloor Grama Panchayat ErnakulamLocal body (LSGI)1 of 48 projects
Choornikara Grama PanchayatGrama Panchayat1 of 48 projects
Edathala PanchayathLocal body (LSGI)1 of 48 projects
Kakkodi Grama Panchayat KozhikodeLocal body (LSGI)1 of 48 projects
Kizhakkambalam Grama PanchayatGrama Panchayat1 of 48 projects
Kochi Municipal Corporation ErnakulamLocal body (LSGI)1 of 48 projects
ThiruvananthapuramLocal body (LSGI)1 of 48 projects
Thrikakkara MuncipalityLocal body (LSGI)1 of 48 projects
Thrikkakara MuncipalityLocal body (LSGI)1 of 48 projects
Thrikkakara Municipality ErnakulamLocal body (LSGI)1 of 48 projects
Thrissur Corporation Office VilvattomLocal body (LSGI)1 of 48 projects
Thriuvanathapuram Corporation Kazhakuttom Zonal OLocal body (LSGI)1 of 48 projects
Thriuvanathapuram Municipal CorporationMunicipal Corporation1 of 48 projects
Trivandrum Municipal CorporationMunicipal Corporation1 of 48 projects
Ulloor Zonal Office Thiruvananthapuram Municipal CorporationMunicipal Corporation1 of 48 projects
Vazayoor Grama PanchayatGrama Panchayat1 of 48 projects
Vazhayur Grama PanchayatGrama Panchayat1 of 48 projects
Vijayapuram Gramapanchayat KottayamLocal body (LSGI)1 of 48 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

K-RERA · Registration filing
Street
VETTU ROAD - ST ANDREWS ROAD
Village
MENAMKULAM
Taluk
THIRUVANANTHAPRUAM
District
Thiruvananthapuram
Pincode
695301
Survey no.
154/8-2,154/5,154/8-2-1,154/8-3
Patta no.
19782,19683
What’s nearby
Schools2 schools within 1km · Library 1.6km away
HealthcareHospital 782m away · 1 clinic within 1km
LifestylePark 1.4km away · 5 restaurants and cafes within 1km
ShoppingSupermarket 358m away · Mall 1.4km away · Convenience store within 1km
Getting around
Expressway 1.8 km · Salem - Kochi - Kanyakumari RoadPrimary road 1.8 km · Kattaikonam - Chandavila - VetturoadRailway line 1.7 kmRailway station 1.7km away (Kaniyapuram)Bus stop within 1km
Water & environment
Water body 151 mCanal 599 m · Parvathy Puthanar
distances only — not a flood assessment
Land, title & encumbrance
Land ownershipBuilt on land that includes third-party owners — a landowner (joint-development) arrangement is declared; confirm the title and your share
As declared by the promoter at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
04

Planning authority

K-RERA · Approved building plan

Kadinamkulam Grama Panchayat

Grama Panchayat
approved 30 Jan 2024 · 2 yrs ago
Building Permit no. SC1-BA(34748)/2024Survey no. 154/8-2,154/5,154/8-2-1,154/8-3
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan SC1-BA(34748)/2024 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

Kadinamkulam Grama Panchayat

Grama panchayat

Has approved 15 RERA projects1% of Kerala.

a mixed market60% apartments · 40% plotted layouts.

Builders
10
On record
704 flats · 152 plots
Since
2021

More layout-heavy than Kerala overall — 40% plots here vs 19% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — K-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — K-RERA does not publish a complaints register. This read cannot speak to them either way.