Complete project overview

K-RERA · Registration filing
Units
86 units
Mix
86 × 2BHK
Booked
86 of 86 filed sold/bookedas declared in the RERA filing
Buildings
1
Land area
2,636 sq m
Floor area
8,272 sq m
Description
CONFIDENT WILLOW

Timeline

Project startedNov 2017
RERA registeredJun 2021
Proposed completionNov 2021
TodayJul 2026
Construction progress

80% overall, as filed

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation100%
Basement(s) and Plinth100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Per-activity completion % from the promoter's construction-task checklist filed with K-RERA — overall is the average across activities, as of that filing. A dated snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

0 of 86 available
TypeArea sq mAvailable
2BHK4,4480 of 86

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system.

02

Builder’s track record

K-RERA · Promoter registration

Confident Projects Residential

PartnershipPromoter type
Malappuram, KeralaBased in
Yes — the promoter declared prior project experienceDeclared prior experience
48Projects
1Cities
2021–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
4,766 homes · 21 plotson the public record across 48 projects
5,97,537 sq mbuilt-up filed
16,390 sq mplotted area
1,90,417 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Thiruvananthapuram Municipal CorporationMunicipal Corporation7 of 48 projects
Thrikkakara MunicipalityMunicipality5 of 48 projects
Thrissur Municipal CorporationMunicipal Corporation5 of 48 projects
Kadinamkulam Grama PanchayatGrama Panchayat3 of 48 projects
Kochi Municipal CorporationMunicipal Corporation3 of 48 projects
Kottayam MunicipalityMunicipality3 of 48 projects
Kozhikode Municipal CorporationMunicipal Corporation3 of 48 projects
Andoorkonam PanchayatLocal body (LSGI)1 of 48 projects
Cheranalloor Grama Panchayat ErnakulamLocal body (LSGI)1 of 48 projects
Choornikara Grama PanchayatGrama Panchayat1 of 48 projects
Edathala PanchayathLocal body (LSGI)1 of 48 projects
Kakkodi Grama Panchayat KozhikodeLocal body (LSGI)1 of 48 projects
Kizhakkambalam Grama PanchayatGrama Panchayat1 of 48 projects
Kochi Municipal Corporation ErnakulamLocal body (LSGI)1 of 48 projects
ThiruvananthapuramLocal body (LSGI)1 of 48 projects
Thrikakkara MuncipalityLocal body (LSGI)1 of 48 projects
Thrikkakara MuncipalityLocal body (LSGI)1 of 48 projects
Thrikkakara Municipality ErnakulamLocal body (LSGI)1 of 48 projects
Thrissur Corporation Office VilvattomLocal body (LSGI)1 of 48 projects
Thriuvanathapuram Corporation Kazhakuttom Zonal OLocal body (LSGI)1 of 48 projects
Thriuvanathapuram Municipal CorporationMunicipal Corporation1 of 48 projects
Trivandrum Municipal CorporationMunicipal Corporation1 of 48 projects
Ulloor Zonal Office Thiruvananthapuram Municipal CorporationMunicipal Corporation1 of 48 projects
Vazayoor Grama PanchayatGrama Panchayatthis project1 of 48 projects
Vazhayur Grama PanchayatGrama Panchayat1 of 48 projects
Vijayapuram Gramapanchayat KottayamLocal body (LSGI)1 of 48 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

K-RERA · Registration filing
Street
Karad Road, Farook College PO
Village
VAZHAYUR
Taluk
KONDOTTY
District
Malappuram
Pincode
673632
Survey no.
Re Sy No 62/6, 62/4
Patta no.
12891
What’s nearby
Schools2 schools within 1km · 6 educational institutions within 1km · College or university 128m away
HealthcareHospital 489m away
LifestyleNo parks within 2km
ShoppingSupermarket 1.5km away · Bank 986m away
Getting around
Expressway 798 m · Calicut-Valanchery-Kuttipuram HighwayPrimary road 2.2 km · Old NH17 RoadRailway line 3.8 kmRailway station 4.1km away (Ferok)2 bus stops within 500m
Water & environment
Water body 582 mRiver 1.5 km · Chaliyar River
distances only — not a flood assessment
04

Planning authority

K-RERA · Approved building plan

Vazayoor Grama Panchayat

Grama Panchayat
approved 4 Mar 2018 · 8 yrs ago
Building Permit no. B2-BA(221614)/2018Survey no. Re Sy No 62/6, 62/4

The promised possession date (15 Nov 2021) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan B2-BA(221614)/2018 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

Grama Panchayat

A village-level local self-government (LSGI) that issues the permit — Kerala's most common approving body. It has approved 268 RERA projects across 13 districts about 1 in 6 in Kerala.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — K-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — K-RERA does not publish a complaints register. This read cannot speak to them either way.