HORIZONMarkets
01

Complete project overview

K-RERA · Registration filing
Units
136 units
Mix
136 × 2BHK
Booked
136 of 136 filed sold/bookedas declared in the RERA filing
Buildings
2
Land area
4,371 sq m
Floor area
11,067 sq m
Description
CONFIDENT DAFFODILS BLOCK A and B

Timeline

Project startedAug 2017
Proposed completionMay 2021
RERA registeredJun 2021
TodayJul 2026
Construction progress

86% overall, as filed

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Installation of lifts, water pumps etc100%
Fire Fighting Fittings and Equipment100%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc100%
Excavation100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Installation of lifts, water pumps etc100%
Fire Fighting Fittings and Equipment100%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc100%
Per-activity completion % from the promoter's construction-task checklist filed with K-RERA — overall is the average across activities, as of that filing. A dated snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

0 of 136 available
TypeArea sq mAvailable
2BHK3,0800 of 64
2BHK3,4650 of 72

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system.

02

Builder’s track record

K-RERA · Promoter registration

Confident Projects Residential

PartnershipPromoter type
Thiruvananthapuram, KeralaBased in
Yes — the promoter declared prior project experienceDeclared prior experience
48Projects
1Cities
2021–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
4,766 homes · 21 plotson the public record across 48 projects
5,97,537 sq mbuilt-up filed
16,390 sq mplotted area
1,90,417 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Thiruvananthapuram Municipal CorporationMunicipal Corporation7 of 48 projects
Thrikkakara MunicipalityMunicipality5 of 48 projects
Thrissur Municipal CorporationMunicipal Corporation5 of 48 projects
Kadinamkulam Grama PanchayatGrama Panchayat3 of 48 projects
Kochi Municipal CorporationMunicipal Corporation3 of 48 projects
Kottayam MunicipalityMunicipality3 of 48 projects
Kozhikode Municipal CorporationMunicipal Corporation3 of 48 projects
Andoorkonam PanchayatLocal body (LSGI)1 of 48 projects
Cheranalloor Grama Panchayat ErnakulamLocal body (LSGI)1 of 48 projects
Choornikara Grama PanchayatGrama Panchayat1 of 48 projects
Edathala PanchayathLocal body (LSGI)1 of 48 projects
Kakkodi Grama Panchayat KozhikodeLocal body (LSGI)1 of 48 projects
Kizhakkambalam Grama PanchayatGrama Panchayat1 of 48 projects
Kochi Municipal Corporation ErnakulamLocal body (LSGI)1 of 48 projects
ThiruvananthapuramLocal body (LSGI)1 of 48 projects
Thrikakkara MuncipalityLocal body (LSGI)1 of 48 projects
Thrikkakara MuncipalityLocal body (LSGI)1 of 48 projects
Thrikkakara Municipality ErnakulamLocal body (LSGI)1 of 48 projects
Thrissur Corporation Office VilvattomLocal body (LSGI)1 of 48 projects
Thriuvanathapuram Corporation Kazhakuttom Zonal OLocal body (LSGI)1 of 48 projects
Thriuvanathapuram Municipal CorporationMunicipal Corporation1 of 48 projects
Trivandrum Municipal CorporationMunicipal Corporation1 of 48 projects
Ulloor Zonal Office Thiruvananthapuram Municipal CorporationMunicipal Corporationthis project1 of 48 projects
Vazayoor Grama PanchayatGrama Panchayat1 of 48 projects
Vazhayur Grama PanchayatGrama Panchayat1 of 48 projects
Vijayapuram Gramapanchayat KottayamLocal body (LSGI)1 of 48 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

K-RERA · Registration filing
Street
Althara Road
Village
ULIYAZHATHURA
Taluk
THIRUVANANTHAPRUAM
District
Thiruvananthapuram
Pincode
695017
Survey no.
Re Sy No 127/3-2, 127/15
Patta no.
27338
What’s nearby
Schools1 school within 1km · 12 educational institutions within 1km · College or university 737m away
HealthcareHospital 195m away · 2 clinics within 1km
LifestylePark 952m away · Gym or sports centre 947m away · 5 restaurants and cafes within 1km
ShoppingSupermarket 737m away · Mall 728m away · Convenience store within 1km
Getting around
Expressway 3.6 kmPrimary road 736 m · Thiruvananthapuram - Nagercoil HighwayRailway line 390 mRailway station 1.4km away (Thiruvananthapuram Central)2 bus stops within 500m
Water & environment
River 297 m · KilliWater body 306 m
distances only — not a flood assessment
04

Planning authority

K-RERA · Approved building plan

Ulloor Zonal Office Thiruvananthapuram Municipal Corporation

Municipal Corporation
approved 1 Jan 2018 · 8 yrs ago
Building Permit no. UE2/BA/76/17Survey no. Re Sy No 127/3-2, 127/15

The promised possession date (1 May 2021) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan UE2/BA/76/17 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

Municipal Corporation / Municipality

A city corporation or municipality that sanctions building & development permits within its own limits. It has approved 871 RERA projects across 12 districts about 1 in 2 in Kerala.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — K-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — K-RERA does not publish a complaints register. This read cannot speak to them either way.