DRA INARA PHASE - IV

TN/35/Building/0172/2025 · TNRERA · https://gethorizon.in/projects/dra-inara-phase-iv-4z0lzjmp

01

Complete project overview

TNRERA · Registration filing
Description
Registration of Ground Floor + 2 Floors with 1 dwelling Unit in each plot, Plot No. 12, 14, 20, 22, 62, 63, 75 and 76 ( Total 8 Dwelling Units) at Thazhambur main road, ottiyambakkam, Chengalpet, comprised in S.Nos. 174/1, 175/1A, 175/2, 176, 177, 178/2A1, 178/2B, 190, 191, 192, 193, 227/1 & 227/2 of Ottiyambakkam Village, TambaramTaluk, Chengalpet District.
Registration no.
TN/35/Building/0172/2025

Timeline

RERA registeredMay 2025
Proposed completionOct 2030
TodaySep 2026
02

Builder’s track record

TNRERA · Builder registration

M/S DRA AADITHYA SOUTH CITY PROJECTS PVT LTD

M/S DRA AADITHYA SOUTH CITY PROJECTS PVT LTDPromoter
5Projects
1Cities
2025–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
5 projectson the public record across 5 projects

These are sums of what the builder has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
CMDA (Chennai Metropolitan Development Authority)CMDA (Chennai Metropolitan Development Authority)2 of 5 projects
Panchayat / Local bodyPanchayat / Local bodythis project2 of 5 projects
Town & Country Planning (DTCP)Town & Country Planning (DTCP)1 of 5 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from M/S DRA AADITHYA SOUTH CITY PROJECTS PVT LTD— the full portfolio →

03

Location

TNRERA · Registration filing
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 1.3km away · Clinic within 2km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Primary road 1.1 km · Vandalur - Mambakkam - Kelambakkam RoadNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
Water body 316 m
distances only — not a flood assessment
04

Government Guidance Rate

Tamil Nadu registration department

In Tamil Nadu it’s called the guideline value.

No government guidance rate is shown for this project.

Tamil Nadu publishes street-level guideline values; its full schedule isn't in Horizon's record yet.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

TNRERA · Approved building plan

Panchayat / Local body

Panchayat / Local body
Planning Permissionapproved 9 May 2025 · 1 yr ago
The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Local body

A municipality, town panchayat or village panchayat. It has approved 234 RERA projects about 1 in 16 in Tamil Nadu.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by TNRERA

07

Other projects nearby

The register · within 25 km

359 residential and mixed-use projects still under way within 25 km. Step out ring by ring:

Of the 38 projects the radar draws within 6 km — every kind, every stage — 35 are residential and mixed-use projects still under way. This list keeps only those, and looks further out.

2 projects within 1 km — showing the nearest 2.

690 m away

CASAGRAND GOLDENGROVE

CASAGRAND PREMIER BUILDER LIMITED

Jan 2025registered
Dec 2027target completion
AuthorityTNRERA
690 m away

CASAGRAND GOLDENGROVE

CASAGRAND PREMIER BUILDER LIMITED

Apr 2025registered
Feb 2028target completion
AuthorityTNRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — TNRERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — TNRERA does not publish a complaints register. This read cannot speak to them either way.
  • Escrow — TNRERA does not publish escrow declarations. Whether buyer money is ring-fenced cannot be read here.