Complete project overview

MahaRERA · Registration filing
Floors
8
Buildings
2
Land area
1,883 sq m
Sanctioned built-up
1,883 sq m

Timeline

RERA registeredApr 2022
Proposed completionDec 2023
TodayJul 2026
Construction progress
Basement (if any)0%
Podiums0%
Stilt floor0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Street Lighting0%
Water conservation…0%
Fire protection an…0%
Electrical meter r…0%
Excavation100%
Plinth100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
OC-readiness100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

OM SAI DEVELOPERS

PartnershipPromoter type
Thane, MAHARASHTRABased in
36Projects
17Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
1,527 homeson the public record across 36 projects
1,25,105 sq mbuilt-up filed
1,20,443 sq mland declared
₹164.49 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Pune Municipal CorporationMunicipal Corporation3 of 14 projects
Others2 of 14 projects
Ahmedabad Urban Development AuthorityUrban Development Authority1 of 14 projects
Assistant Director Town Planning Navi Mumbai Municipal CorporationMunicipal Corporation1 of 14 projects
City and Industrial Development Corporation (CIDCO)Development Authority1 of 14 projects
Dum Dum MunicipalityMunicipality1 of 14 projects
Kalyan Dombivli Municipal CorporationMunicipal Corporation1 of 14 projects
Local Planning AuthorityTown & Country Planning (DTCP)1 of 14 projects
Nagarpanchyat Murbad1 of 14 projects
Ninad Masavkarthis project1 of 14 projects
Vasai Virar City Municipal CorporationMunicipal Corporation1 of 14 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Badlapur (M Cl)
Taluka
Ambarnath
District
Thane
Pincode
421503
Survey no.
SR NO 69 HISSA NO 1A
North boundary
LAND BEARING S NO 79
East boundary
S NO 64
South boundary
LAND BEARING S NO 71
West boundary
LAND BEARING NO 78
What’s nearby
SchoolsNo schools within 2km · Library 1.6km away
HealthcareHospital 576m away · Clinic within 2km
LifestylePark 930m away
ShoppingNo supermarket within 2km
Getting around
Primary road 486 m · MIDC RoadRailway line 1.6 kmRailway station 1.6km away (Badlapur)Bus stop within 1km
Water & environment
Water body 640 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Ninad Masavkar

Building Permit
Survey no. SR NO 69 HISSA NO 1A

The promised possession date (31 Dec 2023) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

The planning authority

The body that sanctioned this project. It has approved 4,607 RERA projects across 33 districts about 1 in 4 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.