HORIZONMarkets
01

Complete project overview

RERA Karnataka · Registration filing
Status
New Project Launch
Towers
9
Land area
30,250 sq m
FAR sanctioned
2.489
Covered area
5,474 sq m
Open area
6,346 sq m

Timeline

RERA registeredJan 2019
Project startedJan 2019
Proposed completionJan 2024
TodayJul 2026
02

Builder’s track record

RERA Karnataka · Promoter registration

Godrej Properties Limited

Mumbai CityBased in
52Projects
22Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
17,268 homes · 865 plotson the public record across 52 projects
31,60,896 sq mbuilt-up filed
2,31,115 sq mplotted area
11,82,706 sq mland declared
₹17595.40 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Municipal Corporation of Greater MumbaiMunicipal Corporation10 of 42 projects
BDA - Bangalore Development AuthorityUrban Development Authority7 of 42 projects
Thane Municipal CorporationMunicipal Corporation4 of 42 projects
BBMP - Bruhat Bengaluru Mahanagara PalikeMunicipal / Corporation2 of 42 projects
City and Industrial Development Corporation (CIDCO)Development Authority2 of 42 projects
Gram PanchayatGram Panchayat2 of 42 projects
Pune Municipal CorporationMunicipal Corporation2 of 42 projects
Ahmedabad Municipal CorporationMunicipal / Corporation1 of 42 projects
BIAPPA - Bangalore Airport Area Planning AuthorityUrban Development Authoritythis project1 of 42 projects
BMRDA - Bangalore Metropolitan Region Development AuthorityUrban Development Authority1 of 42 projects
Hoskote Planning AuthorityTown & Country Planning (DTCP)1 of 42 projects
Hyderabad Metropolitan Development Authority (HMDA)Urban Development Authority1 of 42 projects
Kalyan Dombivli Municipal CorporationMunicipal Corporation1 of 42 projects
Kolkata Municipal CorporationMunicipal Corporation1 of 42 projects
Municipal Corporation Of Greater MumbaMunicipal Corporation1 of 42 projects
Nagpur Metropolitan Region Development AuthorityMetropolitan Development Authority1 of 42 projects
Navi Mumbai Municipal CorporationMunicipal Corporation1 of 42 projects
Panihati MunicipalityMunicipality1 of 42 projects
Pimpri Chinchwad Municipal CorporationMunicipal Corporation1 of 42 projects
Slum Rehabilitation AuthoritySlum Rehabilitation Authority1 of 42 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RERA Karnataka · Registration filing
Taluk
Bengaluru North
District
Bengaluru Urban
Pincode
560062
Address
Sy.No. 130/6 , 131 of Hosahalli Village, Jala Hobli, , Bangalore North Taluk, Bangalore
What’s nearby
SchoolsNo schools within 2km · Library 508m away
HealthcareHospital 1.1km away · 3 clinics within 1km · Pharmacy within 1km
LifestyleNo parks within 2km · Gym or sports centre 885m away · 11+ restaurants and cafes within 1km
ShoppingSupermarket 682m away · Mall 1.5km away · Bank 895m away
Getting around
Expressway 2.0 km · Hebbal Service Road towards BengaluruPrimary road 2.1 kmRailway line 468 mRailway station 4.0km away (Kodigehalli)Bus stop within 1km
Water & environment
Water body 159 m
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹329.56 Cr declared. What that works out to:

24%of the cost is land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RERA Karnataka · Approved building plan

BIAPPA - Bangalore Airport Area Planning Authority

Urban Development Authority
Building Permit

The promised possession date (13 Jan 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

BIAPPA

Urban Development Authority · Bangalore Airport Area Planning Authority

Has approved 328 RERA projects3.8% of Karnataka.

a plotted-layout market30% apartments · 70% plotted layouts. Apartments like yours are the smaller share here — this body mostly approves plotted layouts.

Builders
236
On record
20,448 flats · 19,692 plots
Reach
8 taluks
Since
2017

More layout-heavy than Karnataka overall — 70% plots here vs 38% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Complaints register

10 complaints on RERA Karnataka’s register for this project 20 disposed.

A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.