Sanitary Fittings0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Sanitary Fittings0%
Electrical Fittings0%
Installation of lifts, water pumps etc0%
Fire Fighting Fittings and Equipment0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Sanitary Fittings0%
Electrical Fittings0%
Fire Fighting Fittings and Equipment0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Sanitary Fittings0%
Electrical Fittings0%
The external plumbing and external plastering0%
Completion of terraces floor each building0%
Installation of lifts, water pumps etc0%
Fire Fighting Fittings and Equipment0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Sanitary Fittings0%
Electrical Fittings0%
Overhead and Underground Water Tanks.0%
The external plumbing and external plastering0%
Completion of terraces floor each building0%
Installation of lifts, water pumps etc0%
Fire Fighting Fittings and Equipment0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Sanitary Fittings0%
Fire Fighting Fittings and Equipment0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Sanitary Fittings0%
Electrical Fittings0%
Overhead and Underground Water Tanks.0%
The external plumbing and external plastering0%
Completion of terraces floor each building0%
Fire Fighting Fittings and Equipment0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Sanitary Fittings0%
Electrical Fittings0%
Staircases, Lifts Wells0%
Overhead and Underground Water Tanks.0%
The external plumbing and external plastering0%
Completion of terraces floor each building0%
Installation of lifts, water pumps etc0%
Fire Fighting Fittings and Equipment0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Sanitary Fittings0%
Electrical Fittings0%
Staircases, Lifts Wells0%
Overhead and Underground Water Tanks.0%
The external plumbing and external plastering0%
Completion of terraces floor each building0%
Installation of lifts, water pumps etc0%
Fire Fighting Fittings and Equipment0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Sanitary Fittings0%
Electrical Fittings0%
Overhead and Underground Water Tanks.0%
Installation of lifts, water pumps etc0%
Fire Fighting Fittings and Equipment0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation0%
Basement(s) and Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
Staircases, Lifts Wells0%
Overhead and Underground Water Tanks.0%
The external plumbing and external plastering0%
Completion of terraces floor each building0%
Installation of lifts, water pumps etc0%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation0%
Basement(s) and Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
Staircases, Lifts Wells0%
Overhead and Underground Water Tanks.0%
The external plumbing and external plastering0%
Completion of terraces floor each building0%
Installation of lifts, water pumps etc0%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
Staircases, Lifts Wells0%
Overhead and Underground Water Tanks.0%
The external plumbing and external plastering0%
Completion of terraces floor each building0%
Installation of lifts, water pumps etc0%
Fire Fighting Fittings and Equipment0%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
Staircases, Lifts Wells0%
Overhead and Underground Water Tanks.0%
The external plumbing and external plastering0%
Completion of terraces floor each building0%
Installation of lifts, water pumps etc0%
Fire Fighting Fittings and Equipment0%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
Staircases, Lifts Wells0%
Overhead and Underground Water Tanks.0%
The external plumbing and external plastering0%
Completion of terraces floor each building0%
Installation of lifts, water pumps etc0%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Slabs of Super Structure0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
Staircases, Lifts Wells0%
Overhead and Underground Water Tanks.0%
The external plumbing and external plastering0%
Completion of terraces floor each building0%
Installation of lifts, water pumps etc0%
Fire Fighting Fittings and Equipment0%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation0%
Basement(s) and Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
Staircases, Lifts Wells0%
Overhead and Underground Water Tanks.0%
The external plumbing and external plastering0%
Completion of terraces floor each building0%
Installation of lifts, water pumps etc0%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation0%
Basement(s) and Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
Staircases, Lifts Wells0%
Overhead and Underground Water Tanks.0%
The external plumbing and external plastering0%
Completion of terraces floor each building0%
Installation of lifts, water pumps etc0%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation0%
Basement(s) and Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
Staircases, Lifts Wells0%
Overhead and Underground Water Tanks.0%
The external plumbing and external plastering0%
Completion of terraces floor each building0%
Installation of lifts, water pumps etc0%
Fire Fighting Fittings and Equipment0%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation0%
Basement(s) and Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
Staircases, Lifts Wells0%
Overhead and Underground Water Tanks.0%
The external plumbing and external plastering0%
Completion of terraces floor each building0%
Installation of lifts, water pumps etc0%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation0%
Basement(s) and Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
Staircases, Lifts Wells0%
Overhead and Underground Water Tanks.0%
The external plumbing and external plastering0%
Completion of terraces floor each building0%
Installation of lifts, water pumps etc0%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation0%
Basement(s) and Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
Staircases, Lifts Wells0%
Overhead and Underground Water Tanks.0%
The external plumbing and external plastering0%
Completion of terraces floor each building0%
Installation of lifts, water pumps etc0%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation0%
Basement(s) and Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
Staircases, Lifts Wells0%
Overhead and Underground Water Tanks.0%
The external plumbing and external plastering0%
Completion of terraces floor each building0%
Installation of lifts, water pumps etc0%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation0%
Basement(s) and Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
Staircases, Lifts Wells0%
Overhead and Underground Water Tanks.0%
The external plumbing and external plastering0%
Completion of terraces floor each building0%
Installation of lifts, water pumps etc0%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation0%
Basement(s) and Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
Staircases, Lifts Wells0%
Overhead and Underground Water Tanks.0%
The external plumbing and external plastering0%
Completion of terraces floor each building0%
Installation of lifts, water pumps etc0%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation0%
Basement(s) and Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
Staircases, Lifts Wells0%
Overhead and Underground Water Tanks.0%
The external plumbing and external plastering0%
Completion of terraces floor each building0%
Installation of lifts, water pumps etc0%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation0%
Basement(s) and Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
Staircases, Lifts Wells0%
Overhead and Underground Water Tanks.0%
The external plumbing and external plastering0%
Completion of terraces floor each building0%
Installation of lifts, water pumps etc0%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation0%
Basement(s) and Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
Staircases, Lifts Wells0%
Overhead and Underground Water Tanks.0%
The external plumbing and external plastering0%
Completion of terraces floor each building0%
Installation of lifts, water pumps etc0%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation0%
Basement(s) and Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
Staircases, Lifts Wells0%
Overhead and Underground Water Tanks.0%
The external plumbing and external plastering0%
Completion of terraces floor each building0%
Installation of lifts, water pumps etc0%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation0%
Basement(s) and Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
Staircases, Lifts Wells0%
Overhead and Underground Water Tanks.0%
The external plumbing and external plastering0%
Completion of terraces floor each building0%
Installation of lifts, water pumps etc0%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation0%
Basement(s) and Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
Staircases, Lifts Wells0%
Overhead and Underground Water Tanks.0%
The external plumbing and external plastering0%
Completion of terraces floor each building0%
Installation of lifts, water pumps etc0%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation0%
Basement(s) and Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
Staircases, Lifts Wells0%
Overhead and Underground Water Tanks.0%
The external plumbing and external plastering0%
Completion of terraces floor each building0%
Installation of lifts, water pumps etc0%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation0%
Basement(s) and Plinth0%
Slabs of Super Structure0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
Staircases, Lifts Wells0%
Overhead and Underground Water Tanks.0%
The external plumbing and external plastering0%
Completion of terraces floor each building0%
Installation of lifts, water pumps etc0%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Overhead and Underground Water Tanks.10%
Installation of lifts, water pumps etc15%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc15%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc15%
Installation of lifts, water pumps etc15%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc15%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc15%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc15%
Electrical Fittings15%
Installation of lifts, water pumps etc15%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc15%
Installation of lifts, water pumps etc15%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc15%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc15%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc15%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc15%
The external plumbing and external plastering20%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings20%
Overhead and Underground Water Tanks.20%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings20%
Stilt Floor20%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings25%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings40%
Staircases, Lifts Wells45%
Staircases, Lifts Wells45%
Electrical Fittings50%
Staircases, Lifts Wells50%
Overhead and Underground Water Tanks.50%
Staircases, Lifts Wells50%
Staircases, Lifts Wells50%
Basement(s) and Plinth50%
Overhead and Underground Water Tanks.60%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings60%
Staircases, Lifts Wells65%
Overhead and Underground Water Tanks.65%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings70%
Completion of terraces floor each building75%
Staircases, Lifts Wells80%
Stilt Floor85%
Staircases, Lifts Wells85%
Completion of terraces floor each building90%
The external plumbing and external plastering90%
Completion of terraces floor each building90%
Excavation100%
Basement(s) and Plinth100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
The external plumbing and external plastering100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Excavation100%
Basement(s) and Plinth100%
Excavation100%
Excavation100%
Basement(s) and Plinth100%
Excavation100%
Basement(s) and Plinth100%