HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Units
132 units
Mix
91 × 1 BHK · 41 × 2 BHK
Carpet area
34–52 sq mper-unit range, as filed
Floors
24
Parking
101 spaces
Land area
709 sq m
Sanctioned built-up
6,343 sq m
Recreational open space
270 sq m

Timeline

RERA registeredSep 2020
Proposed completionJan 2025
TodayJul 2026

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

132 units across 3 batches
TypeArea sq mCount
2 BHK5241
1 BHK3488
1 BHK403

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

MahaRERA · Promoter registration

Joyville Shapoorji Housing Private Limited

CompanyPromoter type
Mumbai City, MAHARASHTRABased in
50Projects
4Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
4,043 homeson the public record across 50 projects
5,52,467 sq mbuilt-up filed
2,39,582 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Pune Metropolitan Region Development AuthorityMetropolitan Development Authoritythis project30 of 34 projects
Vasai Virar City Municipal CorporationMunicipal Corporation2 of 34 projects
Jitesh Shrikrishna Bonde1 of 34 projects
Pune Municipal CorporationMunicipal Corporation1 of 34 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Shewalewadi
Taluka
Haveli
District
Pune
Pincode
412307
Survey no.
Parts and portion of : 6 1 part,9 1,9 2,9 5 to 9 20,9 23 to 9 41,10 1 to 10 8,10 10 to 10 16
North boundary
10-1 to 10-8 10-10 to 10-16
East boundary
10-1 to 10-8 10-10 to 10-16
South boundary
Building No 20
West boundary
10-1 to 10-8 10-10 to 10-16
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 1.2km away · Clinic within 2km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 1.3 km · Saswad RoadPrimary road 2.3 km · Hadapsar - Manjari RoadRailway line 1.6 kmRailway station 1.8km away (Sasvad Road)Limited bus connectivity nearby
Water & environment
Water body 282 mCanal 592 m · Mutha Right Bank Canal
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Pune Metropolitan Region Development Authority

Metropolitan Development Authority
Building Permit
Survey no. Parts and portion of : 6 1 part,9 1,9 2,9 5 to 9 20,9 23 to 9 41,10 1 to 10 8,10 10 to 10 16

The promised possession date (31 Jan 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Pune Metropolitan Region Development Authority

Metropolitan / development authority

Has approved 1,013 RERA projectsabout 1 in 20 in Maharashtra.

an apartments market87% apartments · 13% plotted layouts. Apartments like yours are this body's core business.

Builders
604
On record
21,940 flats · 10,299 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
Litigation6 cases on record, earliest 2009
Compliance1 non-compliance notice on record
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

2 complaints on MahaRERA’s register for this project 2 disposed.

A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.