KESAR CLASSIC

P51600054090 · MahaRERA · https://gethorizon.in/projects/kesar-classic-deolaligaon-nashik-8zrvja1a

01

Complete project overview

MahaRERA · Registration filing
Units
55 units
Floors
8
Buildings
2
Parking
71 spaces
Land area
1,532 sq m
Sanctioned built-up
4,163 sq m

Timeline

RERA registeredDec 2023
Proposed completionDec 2025
TodaySep 2026
02

Builder’s track record

MahaRERA · Builder registration

KESAR INFRASPACES LLP

PartnershipPromoter type
Nashik, MAHARASHTRABased in
2Projects
1City
2021–2025Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
65 homeson the public record across 2 projects
5,050 sq mbuilt-up filed
1,832 sq mland declared

These are sums of what the builder has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from KESAR INFRASPACES LLP— the full portfolio →

03

Location

MahaRERA · Registration filing
Village
Deolaligaon
Taluka
Nashik
District
Nashik
Pincode
422101
Survey no.
Survey No. 31/3B/1/2/7, Deolali Shiwar, Nashik
North boundary
ADJ PREM SAHAYOG SOC
East boundary
DP ROAD
South boundary
DP ROAD
West boundary
ADJ SURVEY 31 2A 7
What’s nearby
Schools2 schools within 1km
HealthcareHospital 96m away · 3 clinics within 1km
LifestylePark 1.1km away · Gym or sports centre 936m away
ShoppingNo supermarket within 2km · Mall 816m away
Getting around
Expressway 643 mPrimary road 687 m · Jail RoadRailway line 1.2 kmRailway station 1.2km away (Nashik Road)Limited bus connectivity nearby
Water & environment
River 1.0 km · WaldiWater body 1.9 km
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra IGR — Annual Statement of Rates

In Maharashtra it’s called the ready reckoner rate.

₹31,948per sq yd
₹38,210per sq m
Which rate
residential flat (built)
Matched to
The rate published for the village of “Deolaligaon”.
In force
2026-2027 schedule
Spread
₹22,166₹43,228 per sq yd across the places it was taken over

What this number is — and isn’t

  • The minimum value Maharashtra’s registration department will register a sale at. Stamp duty is usually charged on this or the price in the sale deed, whichever is higher.
  • Not a market price. Sales normally register above it, and how far above varies by place and by project.
  • Its fit depends on the grain the state publishes at. This one is matched at the level of village, and says so above. How Horizon decides what to show.
05

Planning authority

MahaRERA · Approved building plan

Nashik Municipal Corporation

Municipal Corporation
Building Permit
Survey no. Survey No. 31/3B/1/2/7, Deolali Shiwar, Nashik

The promised possession date (31 Dec 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Nashik Municipal Corporation

Municipal corporation

Has approved 821 RERA projectsabout 1 in 24 in Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
692
On record
4,331 flats · 111 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by MahaRERA

07

Other projects nearby

The register · within 25 km

1,072 residential projects still under way within 25 km. Step out ring by ring:

Of the 834 projects the radar draws within 6 km — every kind, every stage — 306 are residential projects still under way. This list keeps only those, and looks further out.

21 projects within 1 km — showing the nearest 6.

100 m awayResidential / Group Housing

AARADHYA RESIDENCY PHASE II

A C JAIN BUILDERS AND DEVELOPERS LLP · Nashik Road · Nashik

Jun 2023registered
Dec 2026target completion
Scale71 flatsAuthorityMahaRERA
120 m awayOthers

TANISHQ PARK ROYALS

M S BUILDERS & DEVELOPERS · Deolaligaon · Nashik

Apr 2024registered
Dec 2026target completion
Government Guidance Rate₹31,948/sq ydScale61 flatsAuthorityMahaRERA
150 m awayResidential / Group Housing

SURYA SUNDER CO-OP HSG. SOC. LTD.

NARAYAN INFRA · Deolaligaon · Nashik

Oct 2025registered
Dec 2029target completion
Government Guidance Rate₹31,948/sq ydScale41 flatsAuthorityMahaRERA
210 m awayMixed

RADHA NAGARI

DEEPAK INFRA AND HOMES PRIVATE LIMITED · Nashik Road · Nashik

Jun 2022registered
Dec 2028target completion
Scale167 flatsAuthorityMahaRERA
320 m awayMixed

SYMPHONY CO-OP HOUSING SOCIETY

J B CONSTRUCTION · Deolaligaon · Nashik

Mar 2024registered
Dec 2026target completion
Government Guidance Rate₹31,948/sq ydScale41 flatsAuthorityMahaRERA
530 m awayOthers

BEL AIR

A C JAIN BUILDERS AND DEVELOPERS LLP · Deolali · Nashik

Jul 2024registered
Dec 2030target completion
Scale191 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.