Complete project overview

MahaRERA · Registration filing
Floors
32
Buildings
6
Parking
302 spaces
Land area
9,657 sq m
Sanctioned built-up
40,714 sq m
Recreational open space
3,443 sq m

Timeline

RERA registeredMar 2024
Proposed completionMay 2028
TodayJul 2026
Construction progress
Podiums0%
Internal finishes0%
Flat fit-out0%
External finishes0%
OC-readiness0%
Internal Roads & F…0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Street Lighting0%
Community Building…0%
Treatment And Disp…0%
Solid Waste Manage…0%
Water conservation…0%
Energy managemcnt0%
Fire protection an…0%
Electrical meter r…0%
Aggregate area of …0%
Open Parking0%
Stairs & lifts13%
Superstructure22%
Excavation100%
Basement (if any)100%
Plinth100%
Stilt floor100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

Kumar Properties Infratech Developers Pvt Ltd

CompanyPromoter type
Pune, MAHARASHTRABased in
5Projects
1City
2021–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
5 projectson the public record across 5 projects
1,42,784 sq mbuilt-up filed
1,37,952 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Pune Municipal CorporationMunicipal Corporationthis project4 of 5 projects
Pmc1 of 5 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Hadapsar
Taluka
Haveli
District
Pune
Pincode
411028
Survey no.
Survey No 178/1A, 178/2A, 178/1B, 178/2B, 179/2/1A/2, 179/2/1A/2A, 179/2/1A/2B, 179/2/1B, 179/2/2
North boundary
By Land Bearing Survey No 179 P
East boundary
By Nala
South boundary
By Land Bearing Survey No 242 P
West boundary
By Nala
What’s nearby
SchoolsNearest school 1.5km away · Library 1.3km away
HealthcareHospital 110m away · 4 clinics within 1km
LifestylePark 590m away · Gym or sports centre 764m away · 3 restaurants and cafes within 1km
ShoppingSupermarket 288m away · Bank 277m away · ATM within 500m
Getting around
Expressway 132 m · Mundhwa RoadPrimary road 1.3 km · Mundhwa RoadRailway line 633 m · Pune - Daund Railway LineRailway station 968m away (Hadapsar Railway Station)Limited bus connectivity nearby
Water & environment
Water body 238 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Pune Municipal Corporation

Municipal Corporation
Building Permit
Survey no. Survey No 178/1A, 178/2A, 178/1B, 178/2B, 179/2/1A/2, 179/2/1A/2A, 179/2/1A/2B, 179/2/1B, 179/2/2
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Pune Municipal Corporation

Municipal corporation

Has approved 1,863 RERA projectsabout 1 in 11 in Maharashtra.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,351
On record
9,749 flats · 439 plots
Reach
3 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
Litigation2 cases on record, earliest 2011
EncumbranceDeclared financial encumbrance on the project
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.