HORIZONMarkets
01

Complete project overview

K-RERA · Registration filing
Units
22 units
Mix
22 × Shops and Showrooms
Booked
10 of 22 filed sold/bookedas declared in the RERA filing
Buildings
1
Land area
688 sq m
Floor area
1,719 sq m
Description
LANDMARK MAPLE COMMERCIAL

Timeline

Project startedJan 2018
RERA registeredJul 2021
Proposed completionMay 2023
TodayJul 2026
Construction progress

87% overall, as filed

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation100%
Basement(s) and Plinth100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Installation of lifts, water pumps etc100%
Fire Fighting Fittings and Equipment100%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc100%
Per-activity completion % from the promoter's construction-task checklist filed with K-RERA — overall is the average across activities, as of that filing. A dated snapshot, not a live tracker.

Find your unit

Filed by type and size, in the batches the promoter registered — not a per-unit listing. Look yours up.

12 of 22 available
TypeArea sq mAvailable
Shops and Showrooms332 of 3
Shops and Showrooms371 of 2
Shops and Showrooms371 of 1
Shops and Showrooms581 of 1
Shops and Showrooms592 of 2
Shops and Showrooms361 of 2
Shops and Showrooms281 of 1
Shops and Showrooms282 of 3
Shops and Showrooms370 of 1
Shops and Showrooms281 of 2
Shops and Showrooms280 of 2
Shops and Showrooms310 of 2

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system.

02

Builder’s track record

K-RERA · Promoter registration

CALICUT LANDMARK BUILDERS AND DEVELOPERS INDIA PRIVATE LIMITED

CompanyPromoter type
Kozhikode, KeralaBased in
Yes — the promoter declared prior project experienceDeclared prior experience
14Projects
1Cities
2021–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
2,689 homeson the public record across 14 projects
3,26,468 sq mbuilt-up filed
1,60,999 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Kodenchery GramapanchayatLocal body (LSGI)4 of 14 projects
Kozhikode Municipal CorporationMunicipal Corporation3 of 14 projects
OlavannaLocal body (LSGI)this project3 of 14 projects
Kodencherry GramapanchayathLocal body (LSGI)2 of 14 projects
Olavanna Grama PanchayatGrama Panchayat2 of 14 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

K-RERA · Registration filing
Street
KUNNATHUPALAM
Village
OLAVANNA
Taluk
Kozhikode
District
Kozhikode
Pincode
673014
Survey no.
148/61
Patta no.
5356
What’s nearby
Schools1 school within 500m · 5 educational institutions within 1km · College or university 1.5km away
HealthcareHospital 985m away · Clinic within 2km
LifestylePark 1.7km away
ShoppingSupermarket 1.8km away · Mall 1.6km away · Bank 160m away
Getting around
Expressway 1.5 km · Kannur-Calicut-Valanchery HighwayPrimary road 3.4 km · Old NH17 RoadRailway line 3.9 kmNo metro or railway within 5km3 bus stops within 500m
Water & environment
River 183 m · Mampuzha RiverWater body 705 m · Mamiyil Pond
distances only — not a flood assessment
Land, title & encumbrance
Land ownershipBuilt on land that includes third-party owners — a landowner (joint-development) arrangement is declared; confirm the title and your share
As declared by the promoter at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
04

Planning authority

K-RERA · Approved building plan

Olavanna

Local body (LSGI)
approved 9 Jan 2018 · 8 yrs ago
Building Permit no. BL-189/17-18Survey no. 148/61

The promised possession date (31 May 2023) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan BL-189/17-18 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

The local self-government (LSGI)

The local body that sanctioned this project. It has approved 404 RERA projects across 14 districts about 1 in 4 in Kerala.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — K-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — K-RERA does not publish a complaints register. This read cannot speak to them either way.