01

Complete project overview

MahaRERA · Registration filing
Units
41 units
Floors
7
Buildings
4
Parking
12 spaces
Land area
1,045 sq m
Sanctioned built-up
3,324 sq m

Timeline

RERA registeredDec 2024
Proposed completionAug 2026
TodaySep 2026
Construction progress
Basement (if any)0%
Podiums0%
Flat fit-out0%
OC-readiness0%
Landscaping & Tree…0%
Open Parking0%
Water Supply10%
Electrical meter r…10%
Water conservation…20%
Stairs & lifts30%
External finishes50%
Sewerage (Chamber,…60%
Internal finishes70%
Excavation100%
Plinth100%
Stilt floor100%
Superstructure100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Builder registration

Prammukh Associates

PartnershipPromoter type
Mumbai City, MAHARASHTRABased in
1Projects
1City
2024–2026Active
Timelineevery project, start → promised completion

The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Talegaon Dabhade (R)
Taluka
Mawal
District
Pune
Pincode
410507
Survey no.
Plot No 155 and 156 CTS No 108 and 117
North boundary
Colony Road
East boundary
Plot No 154 and Plot No 157
South boundary
Colony Road
West boundary
Colony Road
What’s nearby
Schools3 schools within 1km · 3 educational institutions within 1km · College or university 1.7km away
HealthcareHospital 914m away · 1 clinic within 1km
Lifestyle1 park within 500m · Gym or sports centre 953m away · 3 restaurants and cafes within 1km
ShoppingSupermarket 1.1km away · Mall 326m away · ATM within 500m
Getting around
Expressway 948 mPrimary road 3.7 km · Urse Talegaon RoadRailway line 1.0 kmRailway station 1.4km away (Ghorawadi)4 bus stops within 500m
Water & environment
Water body 731 m · Talegaon sanskruti Lake
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra registration department

In Maharashtra it’s called the ready reckoner rate.

No government guidance rate is shown for this project.

Maharashtra's schedule is in Horizon's record, but this project's filed location couldn't be matched to one place with certainty — so no figure is shown rather than a guess.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

MahaRERA · Approved building plan

Talegaon Dabhade Municipal Council

Municipal Council
Building Permit
Survey no. Plot No 155 and 156 CTS No 108 and 117

The promised possession date (31 Aug 2026) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Talegaon Dabhade Municipal Council

Municipal corporation

Has approved 51 RERA projects0.3% of Maharashtra.

an apartments market98% apartments · 2% plotted layouts. Apartments like yours are this body's core business.

Builders
39
On record
118 flats · 6 plots
Since
2019

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by MahaRERA

07

Other projects nearby

The register · within 25 km

1,597 residential projects still under way within 25 km. Step out ring by ring:

Of the 410 projects the radar draws within 6 km — every kind, every stage — 84 are residential projects still under way. This list keeps only those, and looks further out.

10 projects within 1 km — showing the nearest 6.

180 m awayResidential / Group Housing

Prammukh Aisshwaryam

Amit Ramniklal Waghela · Talegaon Dabhade · Mawal

May 2026registered
Jun 2028target completion
Scale14 flatsAuthorityMahaRERA
240 m awayOthers

Antariksha

Mr Indrakumar Rajmal Oswal · Talegaon Dabhade · Mawal

Feb 2025registered
Dec 2028target completion
Scale35 flatsAuthorityMahaRERA
240 m awayOthers

WHITESTONE CELESTIA

WHITESTONE REALTORS · Talegaon Dabhade · Mawal

Mar 2025registered
Dec 2027target completion
Scale27 flatsAuthorityMahaRERA
350 m awayOthers

SWAPNPURTI

A SQUARE BUILDCON · Talegaon Dabhade · Mawal

Mar 2025registered
Mar 2027target completion
Scale46 flatsAuthorityMahaRERA
350 m awayResidential / Group Housing

GOKULDHAM 4TH AVENUES

KULDEEP VIDYANAND JADHAV · Talegaon Dabhade · Mawal

Aug 2026registered
Dec 2027target completion
Scale41 flatsAuthorityMahaRERA
460 m awayResidential / Group Housing

SAI GANESH

ADITYA DEVELOPERS · Talegaon Dabhade · Mawal

Apr 2023registered
Dec 2026target completion
Scale18 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.