Complete project overview

K-RERA · Registration filing
Units
12 units
Mix
12 × 3BHK
Booked
12 of 12 filed sold/bookedas declared in the RERA filing
Buildings
1
Land area
836 sq m
Floor area
1,743 sq m
Description
NANMA DOWNTOWN

Timeline

Project startedDec 2020
RERA registeredAug 2021
Proposed completionJun 2022
TodayJul 2026
Construction progress

88% overall, as filed

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Installation of lifts, water pumps etc100%
Fire Fighting Fittings and Equipment100%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc100%
Per-activity completion % from the promoter's construction-task checklist filed with K-RERA — overall is the average across activities, as of that filing. A dated snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

0 of 12 available
TypeArea sq mAvailable
3BHK700 of 6
3BHK780 of 6

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system.

02

Builder’s track record

K-RERA · Promoter registration

NANMA PROPERTIES LTD

CompanyPromoter type
Ernakulam, KeralaBased in
Yes — the promoter declared prior project experienceDeclared prior experience
5Projects
1Cities
2021–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
1,255 homeson the public record across 5 projects
1,21,851 sq mbuilt-up filed
33,295 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Kochi Muncipal Municipal CorporationMunicipal Corporationthis project2 of 5 projects
Kozhikode Municipal CorporationMunicipal Corporation1 of 5 projects
Marady Grama PanchayatGrama Panchayat1 of 5 projects
Tripunithura MuncipalityLocal body (LSGI)1 of 5 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

K-RERA · Registration filing
Street
AMRITHA NAGAR,EDAPPALLY, ERNAKULAM
Village
EDAPPALLY NORTH
Taluk
Kanayannur
District
Ernakulam
Pincode
683501
Survey no.
13/6-2
Patta no.
13816
What’s nearby
Schools2 schools within 1km · 7 educational institutions within 1km · College or university 629m away
HealthcareHospital 683m away · Clinic within 2km · Pharmacy within 1km
LifestylePark 933m away · Gym or sports centre 693m away · 9 restaurants and cafes within 1km
ShoppingSupermarket 693m away · Mall 1.3km away · Convenience store within 500m
Getting around
Expressway 683 m · Kodungallur-Paravur-Ernakulam HighwayPrimary road 1.7 km · Old National Highway 17Railway line 579 mRailway station 686m away (Idappalli)5 bus stops within 500m
Water & environment
Water body 460 m
distances only — not a flood assessment
04

Planning authority

K-RERA · Approved building plan

Kochi Muncipal Municipal Corporation

Municipal Corporation
approved 17 Nov 2020 · 5 yrs ago
Building Permit no. EYP3/166/008684/2020Survey no. 13/6-2

The promised possession date (15 Jun 2022) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan EYP3/166/008684/2020 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

Kochi Muncipal Municipal Corporation

Municipal corporation / municipality

Has approved 9 RERA projects0.6% of Kerala.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
7
On record
463 flats · 0 plots
Since
2021

More apartment-heavy than Kerala overall — 100% apartments here vs 81% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — K-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — K-RERA does not publish a complaints register. This read cannot speak to them either way.