Timeline

RERA registeredAug 2017
Proposed completionMay 2019
TodayJul 2026
Construction progress
Sewerage (Chamber,…0%
Electrical meter r…20%
Street Lighting25%
Water Supply40%
Internal Roads & F…60%
Landscaping & Tree…60%
Storm Water Drains85%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

BLUE FOREST INFRASTRUCTURE

PartnershipPromoter type
Satara, MAHARASHTRABased in
1Projects
1City
2017–2019Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Phalani
Taluka
Jaoli
District
Satara
Pincode
415012
Survey no.
S NO 124
North boundary
S NO 125
East boundary
S NO 123
South boundary
S NO 110
West boundary
MOUJE MUNAWALE
What’s nearby
SchoolsNearest school 1.2km away · Library 2.0km away
HealthcareHospital 199m away · 12 clinics within 1km · Pharmacy within 500m
LifestylePark 1.1km away · Gym or sports centre 806m away
ShoppingSupermarket 186m away · Convenience store within 1km · Bank 949m away
Getting around
Expressway 23 m · Satara RoadPrimary road 1.6 km · Jawaharlal Nehru MargMetro station 2.5km away (Swargate)Bus stop within 500m
Water & environment
Water body 418 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

District Collector Office, Satara

Collector office
Layout Permit
Survey no. S NO 124

The promised possession date (31 May 2019) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

The planning authority

The body that sanctioned this project. It has approved 4,607 RERA projects across 33 districts about 1 in 4 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.