Description
Registration of Residential Building consisting of Extended Combined Double Basement Floors + Combined Stilt Floor with Club House of Block-1, (Tower-01, 02 & 03), Tower-1 – 1st Floor to 34th Floors with Swimming Pool at 3rd Floor Level with 126 dwelling units, Tower-2 – 1st Floor + 33rd Floors with 128 dwelling units, Tower-3 – 1st Floor + 33rd Floors with 63 dwelling units, totally 317 dwelling units Comprised in S.F.No.8/2B1A, 8/2B1F1A, 8/15, 8/19, 8/20 at Kanathur Reddykuppam Village, Thiruporur Taluk / Panchayat Union, Chengalpattu District.
Registration no.
TN/29/Building/0207/2025

Timeline

RERA registeredJun 2025
Proposed completionJun 2029
TodaySep 2026
02

Builder’s track record

TNRERA · Builder registration

ALTIS PROPERTIES PRIVATE LIMITED.

ALTIS PROPERTIES PRIVATE LIMITED.Promoter
2Projects
1Cities
2024–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
2 projectson the public record across 2 projects

These are sums of what the builder has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
CMDA (Chennai Metropolitan Development Authority)CMDA (Chennai Metropolitan Development Authority)1 of 2 projects
Town & Country Planning (DTCP)Town & Country Planning (DTCP)this project1 of 2 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from ALTIS PROPERTIES PRIVATE LIMITED.— the full portfolio →

03

Location

TNRERA · Registration filing
What’s nearby
SchoolsNearest school 1.7km away
HealthcareHospital 1.4km away
LifestyleNo parks within 2km · Gym or sports centre 1.6km away
ShoppingSupermarket 1.3km away
Getting around
Primary road 79 m · East Coast RoadNo metro or railway within 5km2 bus stops within 500m
Water & environment
Canal 585 m · Buckingham CanalWater body 1.0 km
distances only — not a flood assessment
04

Government Guidance Rate

Tamil Nadu registration department

In Tamil Nadu it’s called the guideline value.

No government guidance rate is shown for this project.

Tamil Nadu publishes street-level guideline values; its full schedule isn't in Horizon's record yet.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

TNRERA · Approved building plan

Town & Country Planning (DTCP)

Town & Country Planning (DTCP)
Planning Permissionapproved 17 Jun 2025 · 1 yr ago
The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Town & Country Planning (DTCP)

Town & country planning

Has approved 756 RERA projectsabout 1 in 5 in Tamil Nadu.

Builders
467
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by TNRERA

07

Other projects nearby

The register · within 25 km

383 residential and mixed-use projects still under way within 25 km. Step out ring by ring:

Of the 38 projects the radar draws within 6 km — every kind, every stage — 36 are residential and mixed-use projects still under way. This list keeps only those, and looks further out.

4 projects within 1 km — showing the nearest 4.

140 m away

SHRINAY GRANDEUR

PREM DEVELOPER

Aug 2025registered
Mar 2030target completion
AuthorityTNRERA
620 m away

CERULEAN

CHAITANYA FOUNDATIONS PRIVATE LIMITED

Jul 2024registered
Jan 2032target completion
AuthorityTNRERA
630 m away

VOORA ONE SEA

VOORA PROPERTY DEVELOPERS PVT LTD.

May 2025registered
Dec 2031target completion
AuthorityTNRERA
990 m away

SEA/LA/VIE

HIRAN PRATHAP VENKATAPURAM

Sep 2025registered
Mar 2027target completion
AuthorityTNRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — TNRERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — TNRERA does not publish a complaints register. This read cannot speak to them either way.
  • Escrow — TNRERA does not publish escrow declarations. Whether buyer money is ring-fenced cannot be read here.