Complete project overview

MahaRERA · Registration filing
Units
326 units
Mix
240 × 2 BHK · 86 × 1 BHK
Carpet area
38–58 sq mper-unit range, as filed
Floors
53
Parking
326 spaces
Land area
2,935 sq m
Sanctioned built-up
32,329 sq m
Recreational open space
2,690 sq m

Timeline

RERA registeredMar 2019
Proposed completionMar 2025
TodaySep 2026
Construction progress
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Internal Roads & F…0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Street Lighting0%
Community Building…0%
Treatment And Disp…0%
Solid Waste Manage…0%
Water conservation…0%
Energy managemcnt0%
Fire protection an…0%
Electrical meter r…0%
Aggregate area of …0%
Closed Parking0%
Excavation100%
Basement (if any)100%
Podiums100%
Plinth100%
Stilt floor100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the builder registered — not a per-flat listing. Look yours up.

326 units across 7 batches
TypeArea sq mCount
2 BHK5143
2 BHK5143
1 BHK3843
1 BHK3943
2 BHK5743
2 BHK5068
2 BHK5843

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

MahaRERA · Builder registration

Jaykali Developers Private Limited

CompanyPromoter type
Mumbai City, MAHARASHTRABased in
7Projects
1City
2019–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
1,377 homeson the public record across 7 projects
1,39,753 sq mbuilt-up filed
20,401 sq mland declared

These are sums of what the builder has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from Jaykali Developers Private Limited— the full portfolio →

03

Location

MahaRERA · Registration filing
Village
Thane (M Corp.)
Taluka
Thane
District
Thane
Pincode
400610
Survey no.
S No 509 and 510 P
North boundary
12 M Wide Road
East boundary
Omega - Northern Lights Tower
South boundary
Podium Garden
West boundary
20 M Wide D P Road
What’s nearby
SchoolsNearest school 1.1km away · Library 888m away
HealthcareHospital 580m away · 3 clinics within 1km · Pharmacy within 1km
LifestylePark 1.5km away · Gym or sports centre 1.5km away · 17+ restaurants and cafes within 1km
ShoppingSupermarket 675m away · Mall 1.0km away · Bank 138m away
Getting around
Expressway 517 mPrimary road 581 m · Eastern Express TurnpikeRailway line 1.0 kmMetro station 862m away (Kapurbawdi Station)10 bus stops within 500m
Water & environment
Water body 245 m
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra IGR — Annual Statement of Rates

In Maharashtra it’s called the ready reckoner rate.

₹60,034per sq yd
₹71,800per sq m
Which rate
residential flat (built)
Matched to
The middle rate across the 101 divisions of “Thane (M Corp.)” — the city's middle, not this project's own division.
In force
2026-2027 schedule
Spread
₹26,923₹1,55,185 per sq yd across the places it was taken over

What this number is — and isn’t

  • The minimum value Maharashtra’s registration department will register a sale at. Stamp duty is usually charged on this or the price in the sale deed, whichever is higher.
  • Not a market price. Sales normally register above it, and how far above varies by place and by project.
  • Its fit depends on the grain the state publishes at. This one is matched at the level of city, and says so above. How Horizon decides what to show.
05

Planning authority

MahaRERA · Approved building plan

Slum Rehabilitation Authority

Slum Rehabilitation Authority
Building Permit
Survey no. S No 509 and 510 P

The promised possession date (30 Mar 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Slum Rehabilitation Authority

Planning authority

Has approved 729 RERA projects3.6% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
554
On record
15,389 flats · 0 plots
Reach
4 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by MahaRERA

07

Other projects nearby

The register · within 25 km

4,818 residential projects still under way within 25 km. Step out ring by ring:

Of the 1,588 projects the radar draws within 6 km — every kind, every stage — 494 are residential projects still under way. This list keeps only those, and looks further out.

70 projects within 1 km — showing the nearest 6.

110 m awayResidential / Group Housing

Shapoorji Pallonji Skyraa at Northern Lights

Jaykali Developers Private Limited · Thane

Feb 2022registered
Dec 2027target completion
Government Guidance Rate₹60,034/sq ydScale332 flatsAuthorityMahaRERA
180 m awayResidential / Group Housing

Embassy One Thane

Tapir Constructions Limited · Thane

Oct 2024registered
Jun 2029target completion
1 open complaintGovernment Guidance Rate₹60,034/sq ydScale232 flatsAuthorityMahaRERA
300 m awayOthers

AVESA

JAGDALE INFRASTRUCTURE PVT. LTD. · Thane

Aug 2021registered
Oct 2026target completion
Government Guidance Rate₹60,034/sq ydScale278 flatsAuthorityMahaRERA
480 m awayResidential / Group Housing

OGC Thane Phase 1

Oberoi Realty Limited · Thane

Oct 2024registered
Jun 2031target completion
1 open complaintGovernment Guidance Rate₹60,034/sq ydScale934 flatsAuthorityMahaRERA
520 m awayResidential / Group Housing

SHRI KRISHNA GOVIND PRASAD CO-OPERATIVE HOUSING SOCIETY LIMITED

GOVIND OJASS EDIFICE PVT. LTD. · Thane

May 2024registered
Dec 2026target completion
Government Guidance Rate₹60,034/sq ydScale66 flatsAuthorityMahaRERA
520 m awayResidential / Group Housing

Om Yashodhan CHSL

SILVER STONE REALTY · Thane

Oct 2024registered
Nov 2026target completion
Government Guidance Rate₹60,034/sq ydScale18 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.