The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
Builder's track record — done
03
Location
MahaRERA · Registration filing
Village
Mira-Bhayandar (M Corp.)
Taluka
Thane
District
Thane
Pincode
401107
Survey no.
Old Survey Number 2, New Survey Number 56, Hissa No.1 & 2
North boundary
D P Road
East boundary
Survey Number 60
South boundary
Survey Number 53 3 and Nalla
West boundary
Survey Number 56 and 54
What’s nearby
Schools2 schools within 500m · 3 educational institutions within 1km
HealthcareHospital 177m away · 5 clinics within 1km · Doctor's clinic within 1km
LifestylePark 881m away · Gym or sports centre 1.8km away · 7 restaurants and cafes within 1km
ShoppingSupermarket 318m away · Bank 740m away
Getting around
Expressway 2.1 km · Western Express HighwayPrimary road 7 m · Mira Bhayandar RoadRailway line 1.4 km · Western Railway Virar to BorivaliRailway station 1.4km away (Mira Road)4 bus stops within 500m
Location — done
04
Government Guidance Rate
Maharashtra IGR — Annual Statement of Rates
In Maharashtra it’s called the ready reckoner rate.
₹60,034per sq yd
₹71,800per sq m
Which rate
residential flat (built)
Matched to
The middle rate across the 101 divisions of “Mira-Bhayandar (M Corp.)” — the city's middle, not this project's own division.
In force
2026-2027 schedule
Spread
₹26,923 – ₹1,55,185 per sq yd across the places it was taken over
What this number is — and isn’t
The minimum value Maharashtra’s registration department will register a sale at. Stamp duty is usually charged on this or the price in the sale deed, whichever is higher.
Not a market price. Sales normally register above it, and how far above varies by place and by project.
Its fit depends on the grain the state publishes at. This one is matched at the level of city, and says so above. How Horizon decides what to show.
Government Guidance Rate — done
05
Planning authority
MahaRERA · Approved building plan
Mira Bhayandar Municipal Cooperation
Building Permit
Survey no. Old Survey Number 2, New Survey Number 56, Hissa No.1 & 2
The occupancy certificate — the proof that isn’t here
An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.
The approving body, at scale
The planning authority
The body that approved this project. It has approved 4,607 RERA projects across 33 districts — about 1 in 4 in Maharashtra.
Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.
Planning authority — done
06
Complaints & litigation
MahaRERA · public record
Complaints register
None on record with MahaRERA against this project.
Only disputes escalated to the authority appear on the record — a private disagreement never filed here would not. A count from the public record, not a verdict.
Court cases, as declared
Declared by the builder
1 case
Number
Forum
Date
RCS/514/2022
Civil Court S D Thane
2022
Not a verdict. A complaint can be dismissed and a case can be won; an order can be appealed.
Not a clean bill. An empty record means nothing was filed with MahaRERA, or that this register doesn’t publish it — never that nothing happened.
Complaints & litigation — done
07
Other projects nearby
The register · within 25 km
3,651 residential projects still under way within 25 km. Step out ring by ring:
34 projects within 1 km — showing the nearest 6.
Mira-BhayandarOthers
HATKESH HEIGHTS - PHASE II
S. M. INFRASTRUCTURES
4 yr 11 mo
Jan 2022registered
Dec 2026target completion
⚠ 1 open complaintGovernment Guidance Rate₹60,034/sq ydScale290 flatsAuthorityMahaRERA