Complete project overview

MahaRERA · Registration filing
Floors
8
Buildings
2
Parking
112 spaces
Land area
1,175 sq m
Sanctioned built-up
3,559 sq m

Timeline

RERA registeredJan 2024
Proposed completionDec 2025
TodayJul 2026
Construction progress
Open Parking0%
OC-readiness50%
Electrical meter r…50%
External finishes60%
Energy managemcnt60%
Fire protection an…60%
Stairs & lifts70%
Street Lighting70%
Water conservation…70%
Flat fit-out80%
Landscaping & Tree…80%
Internal finishes90%
Storm Water Drains90%
Excavation100%
Basement (if any)100%
Podiums100%
Plinth100%
Stilt floor100%
Superstructure100%
Water Supply100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

Mahalaxmi Developers

PartnershipPromoter type
Pune, MAHARASHTRABased in
23Projects
20Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
384 homes · 181 plotson the public record across 23 projects
41,675 sq mbuilt-up filed
8,100 sq mplotted area
36,678 sq mland declared
₹66.74 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Pimpri Chinchwad Municipal CorporationMunicipal Corporationthis project2 of 12 projects
Surat Municipal CorporationMunicipal / Corporation2 of 12 projects
Ahmedabad Municipal CorporationMunicipal / Corporation1 of 12 projects
ChhindwaraTown & Country Planning (DTCP)1 of 12 projects
Local Planning AuthorityTown & Country Planning (DTCP)1 of 12 projects
Maharashtra State Road Development Corporation Limited1 of 12 projects
Nagpur Metropolitan Region Development AuthorityMetropolitan Development Authority1 of 12 projects
Town Planning Pune1 of 12 projects
UjjainTown & Country Planning (DTCP)1 of 12 projects
Vadodara Municipal CorporationMunicipal / Corporation1 of 12 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Punawale
Taluka
Mulshi
District
Pune
Pincode
411033
Survey no.
Sr No 35/1/3 and 35/1/5 P
North boundary
Part of Survey No 35
East boundary
Survey No 35 Part
South boundary
Road
West boundary
Survey No 36
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 481m away · Clinic within 2km · Pharmacy within 1km
LifestyleNo parks within 2km · 5 restaurants and cafes within 1km
ShoppingSupermarket 638m away
Getting around
Expressway 426 m · Katraj - Dehu Road BypassPrimary road 466 m · Service RoadRailway line 3.4 km · Mumbai–Pune RailwayRailway station 3.4km away (Akurdi Railway Station)Limited bus connectivity nearby
Water & environment
River 1.3 km · Pavana RiverWater body 1.6 km
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Pimpri Chinchwad Municipal Corporation

Municipal Corporation
Building Permit
Survey no. Sr No 35/1/3 and 35/1/5 P

The promised possession date (31 Dec 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Pimpri Chinchwad Municipal Corporation

Municipal corporation

Has approved 1,391 RERA projectsabout 1 in 14 in Maharashtra.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,080
On record
9,009 flats · 249 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.