Complete project overview

MahaRERA · Registration filing
Units
24 units
Mix
20 × 1 BHK · 4 × 1 RK
Carpet area
27–40 sq mper-unit range, as filed
Floors
6
Parking
1 spaces
Land area
1,162 sq m
Sanctioned built-up
1,009 sq m

Timeline

RERA registeredMay 2021
Proposed completionDec 2024
TodayJul 2026
Construction progress
Podiums0%
Flat fit-out0%
External finishes0%
OC-readiness0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Water conservation…0%
Electrical meter r…0%
Stairs & lifts20%
Internal finishes25%
Stilt floor60%
Superstructure90%
Excavation100%
Basement (if any)100%
Plinth100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

24 units across 6 batches
TypeArea sq mCount
1 RK384
1 BHK384
1 BHK394
1 BHK404
1 BHK394
1 BHK274

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

MahaRERA · Promoter registration

Raj Construction

PartnershipPromoter type
Raigarh, MAHARASHTRABased in
23Projects
9Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
1,398 homes · 18 plotson the public record across 23 projects
76,179 sq mbuilt-up filed
34,608 sq mland declared
₹195.52 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Kolkata Municipal CorporationMunicipal Corporation5 of 6 projects
Baramati Municipal CorporationMunicipal Corporation1 of 6 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Gimhavane
Taluka
Dapoli
District
Ratnagiri
Pincode
415712
Survey no.
Survey No. 6K
North boundary
Plot No 2
East boundary
Internal Road
South boundary
Grampanchayat Internal Road
West boundary
Small Water Course
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 1.2km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Primary road 115 mNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
River 2.2 km
distances only — not a flood assessment
Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.