Complete project overview
MahaRERA · Registration filing- Floors
- 19
- Buildings
- 6
- Parking
- 288 spaces
- Land area
- 9,125 sq m
- Sanctioned built-up
- 24,715 sq m
- Recreational open space
- 405 sq m
Timeline
Builder’s track record
MahaRERA · Promoter registrationK. R. REAL ESTATE PVT. LTD.
These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.
Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
Location
MahaRERA · Registration filing- Village
- Badlapur (M Cl)
- Taluka
- Ambarnath
- District
- Thane
- Pincode
- 421502
- Survey no.
- Sno 7/1PT 7/2PT 7/3PT 6/1PT 6/2PT 6/3PT 6/4 5/6PT
- North boundary
- 30m wide Badlapur Karjat Road SNo 6by1PT SNo 5PT
- East boundary
- S No 9 PT
- South boundary
- Phase 2 Internal Layout Road
- West boundary
- SNO 7by1PT 7by2PT 5by6PT 6by1PT Phase 5
Planning authority
MahaRERA · Approved building planThe promised possession date (30 Dec 2023) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.
A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.
Kulgaon Badlapur Municipal Council
Municipal corporationHas approved 119 RERA projects — 0.6% of Maharashtra.
an apartments market — 100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.
- Builders
- 102
- On record
- 860 flats · 0 plots
- Since
- 2017
Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.
1 complaint on MahaRERA’s register for this project — 0 disposed, 1 still open.
A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.
What this record cannot tell you
- Build quality — no filing records how well it was actually built.
- Private disputes — only complaints escalated to the authority appear here.
- What it will be worth — the record is the past; it does not price the future.