HORIZONMarkets
01

Complete project overview

K-RERA · Registration filing
Units
74 units
Mix
48 × 3BHK · 26 × 2BHK
Booked
17 of 74 filed sold/bookedas declared in the RERA filing
Buildings
1
Land area
2,319 sq m
Floor area
10,710 sq m
Description
SOWPARNIKA ELANIA

Timeline

Project startedFeb 2018
RERA registeredJun 2021
Proposed completionDec 2025
TodayJul 2026
Construction progress

87% overall, as filed

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation100%
Basement(s) and Plinth100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Installation of lifts, water pumps etc100%
Fire Fighting Fittings and Equipment100%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc100%
Per-activity completion % from the promoter's construction-task checklist filed with K-RERA — overall is the average across activities, as of that filing. A dated snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

57 of 74 available
TypeArea sq mAvailable
2BHK1,57122 of 26
3BHK3,78435 of 48

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system.

02

Builder’s track record

K-RERA · Promoter registration

Sowparnika Projects & Infrasturcture Pvt Ltd

CompanyPromoter type
Kottayam, KeralaBased in
Yes — the promoter declared prior project experienceDeclared prior experience
21Projects
1Cities
2021–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
1,652 homes · 50 plotson the public record across 21 projects
2,02,287 sq mbuilt-up filed
13,768 sq mplotted area
59,509 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Thiruvananthapuram Municipal CorporationMunicipal Corporation5 of 21 projects
Trivandrum Municipal CorporationMunicipal Corporation3 of 21 projects
Adat Grama Panchayath PurnattukaraLocal body (LSGI)1 of 21 projects
Andorkonam Grama PanchayatGrama Panchayat1 of 21 projects
Athirampuzha Grama Panchayath KottayamLocal body (LSGI)1 of 21 projects
ChanganasserymunicipalityLocal body (LSGI)1 of 21 projects
Kalamaserry MuncipalityLocal body (LSGI)1 of 21 projects
KarakulamLocal body (LSGI)1 of 21 projects
Kunnamagalam Grama Panchayath KozhikodeLocal body (LSGI)1 of 21 projects
Muncipal Corporation TrivandrumLocal body (LSGI)1 of 21 projects
Muncipal Office GuruvayurLocal body (LSGI)1 of 21 projects
ThiruvananthapuramLocal body (LSGI)1 of 21 projects
Thiruvananthapuram MuncipalityLocal body (LSGI)1 of 21 projects
Thrissur Muncipal Municipal CorporationMunicipal Corporation1 of 21 projects
Vazhappally Grama PanchayatGrama Panchayatthis project1 of 21 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

K-RERA · Registration filing
Street
Valiyakulam Road, Nr Chethipuzha Village office
Village
CHETHIPPUZHA
Taluk
Changanassery
District
Kottayam
Pincode
686104
Survey no.
83/15-A
Patta no.
3/21104
What’s nearby
Schools2 schools within 1km · 5 educational institutions within 1km · College or university 66m away
HealthcareHospital 483m away · 1 clinic within 1km
LifestylePark 1.8km away · Gym or sports centre 1.7km away · 15+ restaurants and cafes within 1km
ShoppingSupermarket 856m away · Mall 1.9km away · Convenience store within 500m
Getting around
Expressway 989 m · Changanacherry Bypass RoadPrimary road 1.6 km · MC RoadRailway line 944 m · Kottayam-ChanganasserryRailway station 1.4km away (Changanasseri)2 bus stops within 500m
Water & environment
Water body 192 mCanal 1.9 km
distances only — not a flood assessment
04

Planning authority

K-RERA · Approved building plan

Vazhappally Grama Panchayat

Grama Panchayat
approved 6 Jul 2017 · 9 yrs ago
Building Permit no. C3-7878Survey no. 83/15-A

The promised possession date (31 Dec 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan C3-7878 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

Grama Panchayat

A village-level local self-government (LSGI) that issues the permit — Kerala's most common approving body. It has approved 268 RERA projects across 13 districts about 1 in 6 in Kerala.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — K-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — K-RERA does not publish a complaints register. This read cannot speak to them either way.