This project’s MahaRERA registration has lapsed— it expired and was not renewed. A lapsed project may be stalled, finished-but-not-updated, or abandoned; the record stops here and RERA’s ongoing protections may no longer apply. Confirm the current status directly with MahaRERA before you rely on anything below.

01

Complete project overview

MahaRERA · Registration filing
Floors
16
Buildings
2
Parking
121 spaces
Land area
2,500 sq m
Sanctioned built-up
9,037 sq m
Recreational open space
250 sq m

Timeline

RERA registeredFeb 2021
Proposed completionJun 2024
TodayJul 2026
02

Builder’s track record

MahaRERA · Promoter registration

SRI SRI BUILDERS AND DEVELOPERS PROPRIETOR VIJAY KISANLAL AGARWAL

IndividualPromoter type
Kolhapur, MAHARASHTRABased in
1Projects
1City
2021–2024Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Kolhapur (M Corp.)
Taluka
Karvir
District
Kolhapur
Pincode
416012
Survey no.
259 A
North boundary
Remaining Land R S No 691
East boundary
Road 12 Meter
South boundary
Apartment Develope by Vinay Davajekar
West boundary
Road Seven And Half 3 Meter Road
What’s nearby
SchoolsNearest school 1.2km away · College or university 1.2km away · Library 1.6km away
HealthcareHospital 565m away · 3 clinics within 1km
LifestylePark 786m away · Swimming pool within 2km
ShoppingNo supermarket within 2km · Mall 1.9km away
Getting around
Expressway 1.9 kmPrimary road 166 m · Isolation Ring RoadRailway line 2.8 kmRailway station 2.9km away (Shri Chatrapati Shahu Maharaj Terminus)Limited bus connectivity nearby
Water & environment
Water body 443 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Maharashtra Housing and Area Development Authority (MHADA)

Housing Authority
Building Permit
Survey no. 259 A

The promised possession date (30 Jun 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Maharashtra Housing and Area Development Authority (MHADA)

Planning authority

Has approved 438 RERA projects2.2% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
341
On record
13,458 flats · 0 plots
Reach
18 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.