RERA Karnataka · Registration filing
Status
Ongoing
Plots
43 plots
Land parcels
2 survey nos

Timeline

Project startedJun 2025
RERA registeredSep 2025
Proposed completionApr 2029
TodayJul 2026
Construction progress

73% overall, as filed

From the promoter's latest quarterly progress report filed with RERA Karnataka — % complete overall and by stage, as of that filing. A dated snapshot, not a live tracker.

Find your plot

Every plot the builder registered, with the carpet area they filed. Look yours up and check it against what you were shown.

UnitTypeTotal sq m
1Plot121.36
2Plot122
3Plot112.38
4Plot102.76
5Plot153.46
6Plot64.68
7Plot54
8Plot54
9Plot54
10Plot54
11Plot54
12Plot54
13Plot52.35
14Plot95.23
15Plot108
16Plot108
17Plot108
18Plot151
19Plot111.30
20Plot108
21Plot108
22Plot108
23Plot101.89
24Plot118.37
25Plot108
26Plot108
27Plot145.27
28Plot105.39
29Plot108
30Plot108
31Plot124.32
32Plot76.51
33Plot155.35
34Plot136.55
35Plot112.41
36Plot112.41
37Plot112.41
38Plot112.41
39Plot112.41
40Plot112.41
41Plot112.41
42Plot112.41
43Plot117.91

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion.

02

Builder’s track record

RERA Karnataka · Promoter registration

SRINIDHI DEVELOPERS

Partnership FirmPromoter type
MysoreBased in
2Projects
2Cities
2024–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
10 homes · 43 plotson the public record across 2 projects
1,533 sq mbuilt-up filed
488 sq mland declared
₹5.19 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Mysuru Urban Development AuthorityUrban Development Authoritythis project1 of 2 projects
Vice Chairman, UDAUrban Development Authority1 of 2 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RERA Karnataka · Registration filing
Taluk
MYSORE
District
Mysore
Pincode
571123
Address
Survey number 46/1 and 46/2 measuring 2 Acre 9 Guntas , Muradagalli Village, Jayapura Hobli, Mysore , MYSORE , Mysore, Karnataka - 571123
What’s nearby
SchoolsNo schools within 2km
HealthcareNo hospital within 5km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Primary road 4.5 kmNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
Canal 330 mWater body 501 m
distances only — not a flood assessment
Land, title & encumbrance
LandJoint development (JDA) — built on the owner’s land by agreement
ConversionConverted to non-agricultural
LitigationDeclared free of litigation
As declared by the promoter at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
Price analysisdeclared build cost — not a sale price

₹1.84 Cr declared to build 43 plots. What that works out to:

₹4.27 Lakhdeclared cost per plotall-in — land + construction
51%of the cost is land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RERA Karnataka · Approved building plan

Mysuru Urban Development Authority

Urban Development Authority
approved 15 Apr 2025 · 1 yr ago
Layout Permit no. 115/2024-25Survey no. 46/1
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan 115/2024-25 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

Mysuru Urban Development Authority

Urban Development Authority

Has approved 429 RERA projectsabout 1 in 20 in Karnataka.

a plotted-layout market14% apartments · 86% plotted layouts. Your plotted layout is this body's core business.

Builders
342
On record
3,071 flats · 19,105 plots
Reach
11 taluks
Since
2017

More layout-heavy than Karnataka overall — 86% plots here vs 38% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Complaints register

None on record with RERA Karnataka against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.