HORIZONMarkets
01

Complete project overview

GujRERA · Registration filing
Units
808 units
Mix
808 × Residential Unit
Carpet area
34 sq mper unit, as filed
Blocks
5
Parking
23 spaces
Land area
12,738 sq m
Affordable housing
Yes — registered under affordable housingprice caps & eligibility apply

Timeline

Project startedMay 2022
RERA registeredJul 2022
Proposed completionDec 2027
TodayJul 2026
Construction progress

100% overall, as filed

Overall % complete as filed with GujRERA, taken as the slowest of the project's blocks — a snapshot, not a live tracker. Where a BU permission is on record (section 04), that is the firmer completion signal.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

808 units across 1 batch
TypeArea sq mCount
Residential Unit34808

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

GujRERA · Promoter registration

SURAT MUNICIPAL CORPORATION

COMPETENT AUTHORITY/ GOVERNMENTPromoter type
Surat, GujaratBased in
50Projects
2Cities
2018–presentActive
Timelineevery project, start → promised completion
Construction Of 752 DUs Of EWS-II Type at T.P. 25(Mota Varachha) F.P. 165 under PMAYConstruction Of 528 DUs Of EWS-II Type at T.P.27(Utran-Kosad) F.P.167 under PMAYConstruction Of 512 DUs Of EWS-II Type at T.P.27(Utran-Kosad) F.P.180 under PMAYConstruction Of 504 DUs Of EWS-II Type at T.P.27(Utran-Kosad) F.P.191 under PMAYConstruction Of 760 DUs Of EWS-I Type at T.P.27(Utran-Kosad) F.P. 190 under PMAYConstruction Of 80 DUs Of EWS-II Type at T.P.68(Puna-Simada) F.P.R-11 under PMAYConstruction Of 660 DUs Of EWS-I Type at T.P.35(Katargam) F.P. 120 under PMAYConstruction Of 160 DUs Of EWS-I Type at T.P.41(Dindoli),F.P.No.29 under PMAYConstruction Of 408 DUs Of EWS-I Type at T.P.19(Parvat-Magob),F.P.No.100 under PMAYConstruction Of 570 DUs Of EWS-I Type at T.P.19(Parvat-Magob),F.P.No.111/1 under PMAYConstruction Of 208 DUs Of EWS-II Type at T.P.19(Parvat-Magob),F.P.No.112 under PMAYConstruction Of 560 DUs Of EWS-I Type at T.P. 25(Mota Varachha) F.P. 147 under PMAYConstruction Of 192 DUs Of EWS-II Type at T.P.25(Singanpore-Tunki) F.P. 97 under PMAYConstruction Of 1088 DUs Of EWS-II Type at T.P.53(Magob-Dumbhal),F.P.No.82 under PMAYConstruction Of 112 DUs Of EWS-II Type at T.P. 19 (Katargam) F.P. 180 under PMAYConstruction Of 260 DUs Of EWS-II Type at T.P.25(Singanpore-Tunki) F.P. 74 under PMAYConstruction Of 96 DUs Of EWS-II Type at T.P.28(RUNDH-VESU) F.P.32/P-SUB PLOT NO-3 under PMAYConstruction Of 660 DUs Of EWS-II Type at T.P.28(RUNDH-VESU) F.P.32/P-SUB PLOT NO-2 under PMAYSUMAN SURAJ EWS-26 TPS NO 24 (MOTA VARACHHA-UTRAN) FP NO 177 (R-26)SUMAN KESHAV EWS 29 TPS NO 62 (DINDOLI-BHESTAN-BHEDWAD)FP NO 194 (R-26)SUMAN GANGA EWS -28 TPS NO 19 (PARVAT-MAGOB) FP NO 110/3SUMAN BHARGAV EWS-32 TP NO 13 (BHARTHANA-VESU) FP NO 169SUMAN AASTHA EWS-34 TP 42 (BHIMRAD) FP 75SUMAN SARTHI EWS-27 TP 35 (KATARGAM) FP 134SUMAN SADHNA EWS-35 TP 37 (VARIYAV) FP 99SUMAN SANJIVANI EWS-33 TP 42(BHIMRAD) FP 61SUMAN VAIBHAV EWS - 36 TPS NO 36 (VARIYAV) FP NO 90SUMAN PARTH EWS-31 TP 28 (ALTHAN-BHATAR) FP 136SUMAN VANDAN PACKAGE 1 EWS-37 TPS NO 45 (JHANGIRPURA) FP NO 117SUMAN VANDAN PACKAGE 2 EWS-37 TPS NO 45 (JHANGIRPURA) FP NO 117SUMAN VANI EWS-39 TPS NO 44 (JHANGIRABAD) FP NO 06SUMAN KAVYA EWS-42 TPS NO 28 (RUNDH-VESU) FP NO 32 PAIKEE SUB PLOT 1SUMAN MUDRA EWS-48 TPS NO 16 (PAL) FP NO 113SUMAN SNEH EWS-49 TPS NO 16 (PAL) FP NO 114SUMAN ARADHNA EWS-45 TPS NO 43 (BHIMRAD) FP NO 110SUMAN SATHI EWS-38 TPS NO 46 (JHANGIRPURA) FP NO 97SUMAN TAPI EWS-43 TPS NO 42 (BHIMRAD) FP NO 67SUMAN CHANDAN EWS-47 TPS NO 09 (PALANPORE-BHESAN) FP NO 152SUMAN TRUPTI EWS 52 TP 48 (BHESTAN) FP 85Suman Prayag EWS-41SUMAN ARTH EWS-40 TPS NO 24 (MOTA VARACHHA-UTRAN) FP NO 181SUMAN LIPI EWS-53 TP 08 (PALANPORE) FP 131SUMAN ADARSH EWS-54 TP 10 (ADAJAN) FP 17SUMAN UTKARSH EWS-55 TP 27 (UTRAN-KOSAD) FP 178SUMAN SMIT EWS-44 TPS NO 43 (BHIMRAD) FP NO 109SUMAN NUPUR EWS 51 TP 62 (DINDOLI-BHESTAN-BHEDWAD) FP 173SUMAN MAITRI EWS 59 TP 46 (JHANGIRPURA) FP 103SUMAN SHILP EWS 56 TP 13 (VESU-BHARTHANA) F.P. 165+166SUMAN PRAKRUTI EWS 60 TP 48 (BHESTAN) FP 89SUMAN RASHI EWS 57 TP 9 (PALANPORE-BHESHAN) FP 174
Builder DNAthe whole portfolio, summed
27,726 homeson the public record across 50 projects
5,79,496 sq mbuilt-up filed
3,84,123 sq mland declared
₹2274.49 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Surat Municipal CorporationMunicipal / Corporation40 of 50 projects
Surat Urban Development AuthorityUrban Development Authoritythis project10 of 50 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

GujRERA · Registration filing
Taluka
Surat City
District
Surat
Address
TP 46 (JAHANGIRPURA) FP 103, AT VILLAGE - JAHANGIRPURA, TA - ADAJAN, DIST - SURAT.
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 952m away · Clinic within 2km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Primary road 260 mRailway line 588 mMetro station 3.4km away (Botanical Garden)Limited bus connectivity nearby
Water & environment
Canal 417 mWater body 641 m
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹78.11 Cr declared to build 808 flats. What that works out to:

₹5.50 Lakhdeclared unit pricerange on the filing — not a live asking price
₹9.67 Lakhdeclared cost per flatall-in — land + construction
₹2,619/sq ftof carpet area₹28,193/sq m
15%of the cost is land₹859/sq ft of land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

GujRERA · Approved building plan

Surat Urban Development Authority

Urban Development Authority
Building Permitapproved 30 Jul 2022 · 4 yrs ago
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Surat Urban Development Authority

Urban Development Authority

Has approved 895 RERA projectsabout 1 in 19 in Gujarat.

a mixed market65% apartments · 35% plotted layouts.

Builders
734
On record
1,12,087 flats · 25,390 plots
Reach
14 talukas
Since
2008

More layout-heavy than Gujarat overall — 35% plots here vs 6% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Complaints — GujRERA does not publish a complaints register. This read cannot speak to them either way.