HORIZON
Share

SWARA TOWER

P52700051794 · MahaRERA · https://gethorizon.in/projects/swara-tower-phaltan-m-cl-ljvygtlg

01

Complete project overview

MahaRERA · Registration filing
Units
99 units
Floors
7
Buildings
2
Parking
127 spaces
Land area
2,568 sq m
Sanctioned built-up
5,942 sq m

Timeline

RERA registeredJul 2023
Proposed completionJun 2028
TodaySep 2026
Construction progress
Podiums0%
Stilt floor0%
Excavation100%
Basement (if any)100%
Plinth100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
OC-readiness100%
Water Supply100%
Sewerage (Chamber,…100%
Storm Water Drains100%
Landscaping & Tree…100%
Water conservation…100%
Fire protection an…100%
Electrical meter r…100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Builder registration

SWARA BUILDCON

PartnershipPromoter type
Satara, MAHARASHTRABased in
3Projects
3Cities
2018–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
133 homeson the public record across 3 projects
6,960 sq mbuilt-up filed
2,944 sq mland declared
₹4.22 Crdeclared build cost

Build cost is what the builder declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Ahmedabad Municipal CorporationMunicipal / Corporation1 of 3 projects
Phaltan Municipal Council PhaltanMunicipal Councilthis project1 of 3 projects
Rajkot Municipal CorporationMunicipal / Corporation1 of 3 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from SWARA BUILDCON— the full portfolio →

03

Location

MahaRERA · Registration filing
Village
Phaltan (M Cl)
Taluka
Phaltan
District
Satara
Pincode
415523
Survey no.
S NO 65/1, PLOT NO 1+41, BHADKAMKAR NAGAR PHALTAN TAL-PHALTAN, DIST-SATARA 415523
North boundary
OLD S NO 519
East boundary
MUNCIPAL ROAD
South boundary
PLOT NO 2 AND 40
West boundary
PLOT NO 42 43 AND 44
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 1.3km away · Clinic within 2km
LifestyleNo parks within 2km
ShoppingSupermarket 77m away
Getting around
Expressway 1.6 km · Dahiwadi Phaltan RoadPrimary road 550 mRailway line 3.0 kmRailway station 3.0km away (Phaltan)Limited bus connectivity nearby
Water & environment
Water body 762 mCanal 2.0 km · Right Bank Canal
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra registration department

In Maharashtra it’s called the ready reckoner rate.

No government guidance rate is shown for this project.

Maharashtra's schedule is in Horizon's record, but this project's filed location couldn't be matched to one place with certainty — so no figure is shown rather than a guess.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

MahaRERA · Approved building plan

Phaltan Municipal Council Phaltan

Municipal Council
Building Permit
Survey no. S NO 65/1, PLOT NO 1+41, BHADKAMKAR NAGAR PHALTAN TAL-PHALTAN, DIST-SATARA 415523
The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Municipal Corporation

A city municipal corporation that approves projects within its own limits. It has approved 12,653 RERA projects across 34 districts about 1 in 2 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

07

Other projects nearby

The register · within 25 km

48 residential projects still under way within 25 km. Step out ring by ring:

Of the 82 projects the radar draws within 6 km — every kind, every stage — 29 are residential projects still under way. This list keeps only those, and looks further out.

2 projects within 1 km — showing the nearest 2.

480 m awayResidential / Group Housing

J. D. CROWN

J D CROWN · Phaltan

Aug 2020registered
Jun 2026target completion
Scale42 flatsAuthorityMahaRERA
1000 m awayResidential / Group Housing

MANORAMA

NAIK NIMBALKAR INFRA · Phaltan

Jan 2026registered
Dec 2028target completion
Scale12 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.