HORIZONMarkets
01

Complete project overview

ORERA · Registration filing
Units
12 units
Building type
S+4
Land area
583 sq m
Plan valid until
19 May 2025
Amenities
7 filed — Water Supply, Elevators, Community Center, Plantation Area/No., Site Development, External Road …
Description
(Residential Project, S+G+3, No. of Units- 12)

Timeline

Construction startAug 2022
Proposed completionMar 2025
TodayJul 2026
02

Builder’s track record

ORERA · Promoter registration

VISIONTECH HOMES PRIVATE LIMITED

Private Limited CompanyPromoter type
Ganjam, OdishaBased in
2Projects
1City
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
37 homeson the public record across 2 projects
1,769 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

ORERA · Registration filing
District
Ganjam
Pincode
760001
What’s nearby
Schools1 school within 1km · Library 1.2km away
HealthcareHospital 783m away · 10 clinics within 1km · Doctor's clinic within 1km
LifestyleNo parks within 2km · 5 restaurants and cafes within 1km
ShoppingNo supermarket within 2km · Bank 773m away
Getting around
Expressway 1.1 km · Aska RoadPrimary road 781 m · Utkal Ashram RoadRailway line 1.6 kmRailway station 1.6km away (Brahmapur)Limited bus connectivity nearby
Water & environment
Water body 294 m
distances only — not a flood assessment
Land, title & encumbrance
Land parcels4 parcels · 583 sq m total
VillageAnkuli
As declared by the promoter at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
04

Planning authority

ORERA · Approved building plan

Berhampur Development Authority

Urban Development Authority
Building Permit

The promised possession date (31 Mar 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Berhampur Development Authority

Development Authority

Has approved 71 RERA projectsabout 1 in 17 in Odisha.

an apartments market86% apartments · 14% plotted layouts. Apartments like yours are this body's core business.

Builders
46
On record
2,784 flats · 1,080 plots
Reach
13 pincodes
Since
2019

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — ORERA does not publish quarterly progress reports. How far along it actually is cannot be read here.