Still due — nearest target completion first, using the revised date where one is filed.
Group Housing
ARCHI THE HARMONY
SHREEJI ENTERPRISES · Udaipur
5 yr 6 mo
Mar 2021registered
Sep 2026target completion
Units76 unitsCarpet area122–150 sq mMix44 × 3 BHK 1st to 11th · 22 × 4 BHK 1st to 11th
Plotted Development
OMKARESHWAR VIHAR
KISHAN LAL JAT · Udaipur
9 mo
Dec 2025registered
Sep 2026target completion
Plots43 plotsLand area7,958 sq m
Group Housing
Construction of LIG (G+3) 56 Flats at South Ext. Scheme(Balicha) Udaipur
RAJASTHAN HOUSING BOARD · Udaipur
4 yr 3 mo
Jun 2022registered
Sep 2026target completion
Units56 unitsMix56 × G+3Carpet area42 sq m
Plotted Development
KRISHNA KANEHAIYA VIHAR
MAHAVEER BANSAL · Udaipur
1 mo
Aug 2026registered
Sep 2026target completion
Plots52 plotsLand area7,971 sq m
Plotted Development
Mani Nagar
mahesh Chandra Sharma · Udaipur
2 mo
Aug 2026registered
Oct 2026target completion
Plots39 plotsLand area17,419 sq m
Group Housing
GANPATI GREENS
SHREE GANPATI AFFORDABLE HOMES LLP · Udaipur
7 yr 11 mo
Nov 2018registered
Oct 2026target completion
⚠ possession revisedUnits354 unitsCarpet area27–439 sq mMix234 × RESIDENTIAL LIG FLATS · 108 × RESIDENTIAL EWS FLATS
Plotted Development
SHRI ADINATH NAGAR F BLOCK
Rupa ji · Udaipur
8 mo
Mar 2026registered
Nov 2026target completion
Plots113 plotsLand area19,235 sq m
Plotted Development
Nakoda Residency
MANOJ NAGORI · Udaipur
4 mo
Jul 2026registered
Nov 2026target completion
Plots34 plotsLand area5,261 sq m
Plotted Development
SRM NAGAR II
HEMENDRA SINGH RATHORE · Udaipur
4 mo
Jul 2026registered
Nov 2026target completion
Plots33 plotsLand area5,665 sq m
Plotted Development
MAYA NAGAR
RAJENDRA KUMAR KEER · Udaipur
9 mo
Mar 2026registered
Dec 2026target completion
Plots33 plotsLand area11,296 sq m
Plotted Development
RAJ VIHAR 2
NITESH PAHADIYA · Udaipur
5 mo
Jul 2026registered
Dec 2026target completion
Plots22 plotsLand area5,099 sq m
Group Housing
URBAN HEIGHTS
URBAN HEIGHTS · Udaipur
2 yr 9 mo
Mar 2024registered
Dec 2026target completion
Units20 unitsCarpet area96–97 sq mMix9 × Flat No. 102 · 104
Group Housing
ARCHI'S THE LOTUS COUNTY
ARCHI BUILDMART PRIVATE LIMITED · Udaipur
6 yr 9 mo
Mar 2020registered
Dec 2026target completion
⚠ possession revisedUnits396 unitsMix396 × 1 BHKCarpet area53 sq m
Group Housing
MAHADEV TOWER
SHUBH CONSTRUCTIONS · Udaipur
3 yr 6 mo
Jun 2023registered
Dec 2026target completion
⚠ possession revisedUnits45 unitsCarpet area55–69 sq mMix5 × 2 BHK Flat (101-501) · 5 × 2 BHK Flat (102-502)
Group Housing
HITAWALA RISING STAR
RISING STAR CONSTRUCTION · Udaipur
5 yr 11 mo
Jan 2021registered
Dec 2026target completion
⚠ possession revisedUnits106 unitsCarpet area80–130 sq mMix18 × Flat Type 101 TO 901 · 18 × Flat Type 105 TO 905
Group Housing
SANSKAR PEARL
SANSKAR BUILDESTATE PRIVATE LIMITED · Udaipur
4 yr 5 mo
Jul 2022registered
Dec 2026target completion
Units28 unitsMix26 × 4BHK FLAT Ground - Sixth, Eighth - Eleventh & Thirteenth - Fourteenth · 2 × 5BHK FLAT Seventh & TwelfthCarpet area197–353 sq m
Plotted Development
PRATAP GREENS
KULDEEP SINGH SHAKTAWAT · Udaipur
1 yr 2 mo
Nov 2025registered
Jan 2027target completion
Plots12 plotsLand area2,399 sq m
Group Housing
ROCK CELESTIAL
ROCK BUILDCON · Udaipur
1 yr 6 mo
Jul 2025registered
Jan 2027target completion
Units12 unitsMix6 × 4BHK FLAT NO. 102 TO 602 (GROUND FLOOR TO FIFTH FLOOR) · 6 × 4BHK FLAT NO. 101 TO 601 (GROUND FLOOR TO FIFTH FLOOR)Carpet area169–171 sq m
Plotted Development
SHREE ADINATH NAGAR- A BLOCK
Kalu · Udaipur
1 yr 2 mo
Jan 2026registered
Mar 2027target completion
⚠ possession revisedPlots59 plotsLand area12,740 sq mCompletion deadline extended1 extension on record — latest to 9 Mar 2027
Plotted Development
SHRI ADINATH NAGAR- B BLOCK
DINESH JAIN · Udaipur
1 yr 1 mo
Feb 2026registered
Mar 2027target completion
⚠ possession revisedPlots90 plotsLand area16,429 sq mCompletion deadline extended1 extension on record — latest to 9 Mar 2027
Plotted Development
SHRI ADINATH NAGAR- D BLOCK
RANGA · Udaipur
1 yr 1 mo
Feb 2026registered
Mar 2027target completion
⚠ possession revisedPlots110 plotsLand area18,878 sq mCompletion deadline extended1 extension on record — latest to 9 Mar 2027
Plotted Development
SHRI ADINATH NAGAR - E BLOCK
ANKIT JAIN · Udaipur
1 yr 5 mo
Oct 2025registered
Mar 2027target completion
⚠ possession revisedPlots98 plotsLand area17,394 sq mCompletion deadline extended1 extension on record — latest to 9 Mar 2027
Plotted Development
SAGAR GREEN F BLOCK
Bhanwari Bai · Udaipur
9 mo
Jun 2026registered
Mar 2027target completion
Plots58 plotsLand area11,671 sq m
Plotted Development
MOHAN KUNJ II MAVALI
PAWAN GOYAL · Udaipur
1 yr 4 mo
Nov 2025registered
Mar 2027target completion
Plots100 plotsLand area16,621 sq m
Plotted Development
MOHAN KUNJ III MAVALI
RENU GOYAL · Udaipur
1 yr 4 mo
Nov 2025registered
Mar 2027target completion
Plots93 plotsLand area17,948 sq m
Plotted Development
MOHAN KUNJ-I MAVALI
Manit Goyal · Udaipur
1 yr 4 mo
Nov 2025registered
Mar 2027target completion
Plots53 plotsLand area11,889 sq m
Group Housing
AKME SUNCITY HOMES- III
AKME SARVODAY DREAMVENTURES LLP · Udaipur
4 yr 3 mo
Dec 2022registered
Mar 2027target completion
⚠ possession revisedUnits162 unitsCarpet area30–46 sq mMix96 × LIG House on Plot No. 1 to 48 · 102 to 149
Group Housing
KANAK GHAR
KRATICONSTRUCTION PROPRIETOR ASHOKSONI · Udaipur
3 yr 11 mo
Apr 2023registered
Mar 2027target completion
Units11 unitsMix4 × 3 BHK (Second Floor, Third Floor) · 4 × 3 BHK (Ground, First Floor) · 3 × 3 BHK (Fourth Floor, Fifth Floor)Carpet area127–282 sq m
Group Housing
ROYAL ALPINE
PINE ENTERPRISES · Udaipur
4 yr 9 mo
Jun 2022registered
Mar 2027target completion
Units47 unitsCarpet area55–81 sq mMix8 × 3BHK - FLAT 1 · 8 × 2BHK - FLAT 5
Group Housing
The ARC by Mundra
MUNDRA ARC LLP · Udaipur
3 yr 3 mo
Dec 2023registered
Mar 2027target completion
Units70 unitsCarpet area229–317 sq mMix1 × FLAT NO 201 FIRST FLOOR 4BHK · 1 × FLAT NO 403 THIRD FLOOR 4BHK
Group Housing
THE ICONIC
PARAMOUNT ROCK INFRA · Udaipur
2 yr 6 mo
Sep 2024registered
Mar 2027target completion
Units36 unitsCarpet area167–224 sq mMix7 × 3BHK Flat No. 103-703 (Ground to 6th Floor) · 7 × 4BHK Flat No. 101-701 (Ground Floor 6th Floor)
Plotted Development
SHRI ADINATH NAGAR-C BLOCK
CHAMPA LAL · Udaipur
1 yr 2 mo
Feb 2026registered
Apr 2027target completion
Plots104 plotsLand area17,679 sq m
Plotted Development
GULSHANE CHISHT SOCIETY
MUSTAFA ALI · Udaipur
1 yr 2 mo
Mar 2026registered
May 2027target completion
Plots9 plotsLand area1,776 sq m
Mixed (Residential And Commercial)
HITAWALA BLUE DIAMOND
BLUE DIAMOND · Udaipur
6 yr
Jun 2021registered
Jun 2027target completion
Units64 unitsCarpet area79–128 sq mMix9 × Flat Type-5 (1 to 9 Floor) · 9 × Flat Type-6 (1 to 9 Floor)
Group Housing
RAJAT RESIDENCY
Navroop Rajat Infraprojects LLP · Udaipur
11 mo
Jul 2026registered
Jun 2027target completion
Units80 unitsCarpet area28–56 sq mMix8 × EWS (1 BHK) FLAT NO.G01 to 701 · 8 × LIG (2 BHK) FLAT NO.G02 to 702
Plotted Development
MANTHAN VALLY VIHAR
AAKUDA GAMETI · Udaipur
1 yr
Jun 2026registered
Jun 2027target completion
Plots41 plotsLand area14,345 sq m
Group Housing
NAVRATAN SKYLINE
GOVERDHAN LAL TAK · Udaipur
1 yr 6 mo
Dec 2025registered
Jun 2027target completion
Units20 unitsMix10 × Flat No. 2, 4, 6, 8, 10, 12, 14, 16, 18, 20 · 9 × Flat No. 1, 3, 5, 9, 11, 13, 15, 17, 19 · 1 × Flat No. 7Carpet area72–154 sq m
Group Housing
BORDIA'S THE VIEW
DEEPAK BORDIA · Udaipur
1 yr 11 mo
Jul 2025registered
Jun 2027target completion
Units18 unitsCarpet area186–208 sq mMix5 × Flat No. G-2 · 102
Group Housing
SAMBHAVNATH COMPLEX A BLOCK (RISHAB TOWER)
SAMBHAVNATH COMPLEX LIMITED · Udaipur
3 yr 6 mo
Dec 2023registered
Jun 2027target completion
Units105 unitsCarpet area21–90 sq mMix8 × Flat No. 101 · 201
Group Housing
SHREEJI EXOTICA PHASE 2
SHREEJI DEVELOPERS · Udaipur
3 yr 9 mo
Sep 2023registered
Jun 2027target completion
Units71 unitsMix47 × 3 BHK · 24 × 2 BHKCarpet area80–129 sq m
Plotted Development
SHRI PRABAL VIHAR
Gotam Lal Meena · Udaipur
1 yr 8 mo
Nov 2025registered
Jul 2027target completion
Plots14 plotsLand area2,549 sq m
Plotted Development
MANSURI MARKET
MUKHTIYAR MOHAMMED · Udaipur
1 yr 6 mo
Jan 2026registered
Jul 2027target completion
Plots49 plotsLand area5,019 sq m
Plotted Development
SHRI GAJANAND PRIME CITY SANWAD
CHANCHAL KUMAR SONI · Udaipur
1 yr 3 mo
Jun 2026registered
Sep 2027target completion
Plots20 plotsLand area4,074 sq m
Group Housing
EKAYA EIGHT
EKAYA REALTY LLP · Udaipur
3 yr 2 mo
Jul 2024registered
Sep 2027target completion
⚠ possession revisedUnits8 unitsMix8 × 4 BHK (G-1, 101, 201, 301, 401, 501, 601, 701)Carpet area244 sq m
Group Housing
SERENE CASA
PRAHAR DEVELOPERS PRIVATE LIMITED · Udaipur
3 yr 9 mo
Dec 2023registered
Sep 2027target completion
Units29 unitsCarpet area76–138 sq mMix6 × FLAT No. 101,201,301,401,501,601 · 6 × FLAT No. 102,202,302,402,502,602
Group Housing
sanchi splendid
ARNATH INFRAVISION LLP · Udaipur
5 yr
Oct 2022registered
Oct 2027target completion
Units53 unitsMix18 × 3 bhk (type 2) · 18 × 4 bhk (type 3) · 17 × 3 bhk (type 1)Carpet area108–140 sq m
Group Housing
AMAAYA
ADDOR LIFESPACE · Udaipur
2 yr 3 mo
Aug 2025registered
Nov 2027target completion
Units20 unitsMix20 × Block-B- B1 to B2Carpet area264 sq m
Group Housing
Jupiter Appartment
Jupiterr Infra Builder · Udaipur
3 yr 3 mo
Sep 2024registered
Dec 2027target completion
Units89 unitsCarpet area55–146 sq mMix10 × 2BHK(2,102,202,302,402,502,602,702,802,902) · 10 × 3BHK(8,108,208,308,408,508,608,708,808,908)
Group Housing
Trustroof Rhythm
Trustroof Infra Projects · Udaipur
2 yr 2 mo
Nov 2025registered
Jan 2028target completion
Units35 unitsCarpet area114–179 sq mMix9 × 3 BHK (Flat No. G02 · 102
Group Housing
Mandot Prime
Nirvan Enterprises · Udaipur
3 yr 11 mo
Feb 2024registered
Jan 2028target completion
Units24 unitsCarpet area174–174 sq mMix17 × G-1,G-3,G-4,101,103,104,201,203,204,301,303,304,401,403,404,503,504 · 5 × G-2,102,202,302,402
Group Housing
AADI-SHIV HEIGHTS
AADI-SHIV INFRA BUILDERS PRIVATE LIMITED · Udaipur
3 yr 3 mo
Dec 2024registered
Mar 2028target completion
Units20 unitsCarpet area83–183 sq mMix5 × 3BHK FLATS G-3 TO 403(GROUND FLOOR TO FOURTH FLOOR) · 4 × 3BHK FLATS G-1 TO 301 (GROUND FLOOR TO THIRD FLOOR)
Group Housing
AISHWARYAM RESIDENCY
Mahalaxmi Buildhome Limited · Udaipur
7 yr 2 mo
Jan 2021registered
Mar 2028target completion
⚠ possession revisedUnits156 unitsCarpet area58–105 sq mMix48 × 3 BHK FLAT TYPE-1 (G + 11 Floor) · 36 × 3 BHK FLAT TYPE-3 (G + 11 Floor)
Group Housing
ARCHI'S THE ADDRESS
ARCHI ARIHANT LLP · Udaipur
4 yr 3 mo
Dec 2023registered
Mar 2028target completion
Units90 unitsCarpet area183–311 sq mMix14 × 4 BHK FLAT No.101,106,201,206,301,306,401,406,501,506,601,606,701,706 · 14 × 4 BHK FLAT No. 102,105,202,205,302,305,402,405,502,505,602,605,702,705
Group Housing
RADHE KRISHNA VRINDAVANN-1
Mahalaxmi Buildhome Limited · Udaipur
3 yr 10 mo
May 2024registered
Mar 2028target completion
Units49 unitsCarpet area96–156 sq mMix9 × Flat No. G-01 · 101
Group Housing
SERENE LUXE
ARTH ASSOCIATES · Udaipur
4 yr 10 mo
May 2023registered
Mar 2028target completion
Units26 unitsCarpet area135–249 sq mMix7 × 4 BHK (Ground · First
Group Housing
GALAXY SOLITAIRE
M/S. GALAXY BUILDERS · Udaipur
2 yr 6 mo
Oct 2025registered
Apr 2028target completion
Units24 unitsCarpet area75–117 sq mMix6 × Flat No. G003 · 103
Group Housing
SAWARIYA THE IMPERIAL
RAKESH KUMAR GUPTA · Udaipur
3 yr 1 mo
Mar 2025registered
Apr 2028target completion
Units12 unitsMix6 × Flat No. G-1, G-2, 101, 102, 201, 202 · 6 × Flat No. 301, 302, 401, 402, 501, 502Carpet area183 sq m
Group Housing
SKYLINE
SIDDHATVA ENCLAVE PRIVATE LIMITED · Udaipur
4 yr 7 mo
Oct 2023registered
May 2028target completion
Units29 unitsCarpet area60–131 sq mMix8 × Flat No. 04 · 05 (Ground to Third Floor) (3 BHK)
Group Housing
Jivanta Mansion
Jivanta Construction · Udaipur
2 yr 11 mo
Jun 2025registered
May 2028target completion
Units8 unitsMix4 × 4BHK (2,102,202,302) · 4 × 4BHK (1,101,201,301)Carpet area125–130 sq m
Group Housing
SURREAL MERAKI
M/s SURREAL HOMES LLP · Udaipur
6 yr 10 mo
Jan 2022registered
Nov 2028target completion
Units12 unitsMix12 × Flat No. 1-12Carpet area136 sq m