HORIZON
Share

Akshar Estrella

P52000078479 · MahaRERA · https://gethorizon.in/projects/akshar-estrella-chanje-uran-ua4uwskx

01

Complete project overview

MahaRERA · Registration filing
Units
186 units
Floors
17
Buildings
2
Parking
248 spaces
Land area
3,618 sq m
Sanctioned built-up
10,853 sq m

Timeline

RERA registeredDec 2024
Proposed completionMar 2029
TodaySep 2026
Construction progress
Podiums0%
Flat fit-out0%
External finishes0%
OC-readiness0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Treatment And Disp…0%
Solid Waste Manage…0%
Water conservation…0%
Fire protection an…0%
Electrical meter r…0%
Internal finishes10%
Superstructure85%
Stairs & lifts90%
Excavation100%
Basement (if any)100%
Plinth100%
Stilt floor100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Builder registration

Geomatrix Enterprises LLP

PartnershipPromoter type
Thane, MAHARASHTRABased in
1Projects
1City
2024–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Chanje
Taluka
Uran
District
Raigarh
Pincode
400702
Survey no.
Survey No. 84/1
North boundary
Deolwadi
East boundary
9 Mtr DP Road
South boundary
12 Mtr DP Road
West boundary
Open space
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 202m away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Primary road 239 mRailway line 951 mRailway station 1.6km away (Uran City)5 bus stops within 500m
Water & environment
Water body 190 m
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra registration department

In Maharashtra it’s called the ready reckoner rate.

No government guidance rate is shown for this project.

Maharashtra's schedule is in Horizon's record, but this project's filed location couldn't be matched to one place with certainty — so no figure is shown rather than a guess.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

MahaRERA · Approved building plan

Uran Municipal Council

Municipal Council
Building Permit
Survey no. Survey No. 84/1
The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Uran Municipal Council

Municipal corporation

Has approved 9 RERA projects0% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
8
On record
186 flats · 0 plots
Since
2024

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by MahaRERA

07

Other projects nearby

The register · within 25 km

1,943 residential projects still under way within 25 km. Step out ring by ring:

Of the 243 projects the radar draws within 6 km — every kind, every stage — 59 are residential projects still under way. This list keeps only those, and looks further out.

10 projects within 1 km — showing the nearest 6.

60 m awayOthers

Horizon Landmark

GREENSCAPE KALPANA STRUCT CON · Chanje · Uran

Jul 2025registered
Dec 2030target completion
Scale323 flatsAuthorityMahaRERA
160 m awayResidential / Group Housing

MAHAAVIR LABDHI PHASE 1

MAHAAVIR BUILDCON LLP · Mhatvali · Uran

May 2022registered
Dec 2027target completion
Scale386 flatsAuthorityMahaRERA
200 m awayOthers

BALAJI ICON

Shree Balaji Developers · Chanje · Uran

Jul 2024registered
Mar 2029target completion
Scale186 flatsAuthorityMahaRERA
200 m awayOthers

Balaji Planet

PLANETNOVA DEVELOPMENTS LLP · Uran

Jun 2025registered
Dec 2029target completion
Government Guidance Rate₹30,017/sq ydScale75 flatsAuthorityMahaRERA
700 m awayMixed

Shree Narayan Residency

SHREE GANESH BUILDERS AND DEVELOPERS · Dronagiri · Uran

Mar 2026registered
Dec 2028target completion
Scale15 flatsAuthorityMahaRERA
870 m awayMixed

Shiv Enclave

Cielo Heights · Uran

Aug 2025registered
Dec 2029target completion
Government Guidance Rate₹30,017/sq ydScale59 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.