This project’s MahaRERA registration has lapsed— it expired and was not renewed. A lapsed project may be stalled, finished-but-not-updated, or abandoned; the record stops here and RERA’s ongoing protections may no longer apply. Confirm the current status directly with MahaRERA before you rely on anything below.

01

Complete project overview

MahaRERA · Registration filing
Project name
AMBARISH CHS LTD
Units
116 units
Floors
17
Buildings
2
Parking
1 spaces
Land area
1,346 sq m

Timeline

RERA registeredDec 2020
Proposed completionJun 2025
TodaySep 2026
02

Builder’s track record

MahaRERA · Builder registration

PEERLESS CONSTRUCTIONS PRIVATE LIMITED

CompanyPromoter type
Mumbai Suburban, MAHARASHTRABased in
1Projects
1City
2020–2025Active
Timelineevery project, start → promised completion

The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Kurla
Taluka
Kurla
District
Mumbai Suburban
Pincode
400024
Survey no.
12 pt bldg 113, plot 98
North boundary
12 mtr wide road
East boundary
15 mtr wide road
South boundary
nulla
West boundary
open
What’s nearby
Schools1 school within 1km
HealthcareHospital 79m away · 2 clinics within 1km · Doctor's clinic within 1km
LifestylePark 1.1km away · Gym or sports centre 1.8km away · 4 restaurants and cafes within 1km
ShoppingSupermarket 242m away · Bank 176m away
Getting around
Expressway 709 m · Santa Cruz – Chembur Link RoadPrimary road 848 m · Lal Bahadur Shastri MargRailway line 286 mRailway station 364m away (Kurla)6 bus stops within 500m
Water & environment
Water body 188 m
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra registration department

In Maharashtra it’s called the ready reckoner rate.

No government guidance rate is shown for this project.

Mumbai's ready reckoner is addressed by city survey (CTS) number inside a named village, and this filing declares neither — its village field holds a ward or a taluka. Naming one of the zones around it would be a guess, and inside a single division the rates run three-fold.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

MahaRERA · Approved building plan

Maharashtra Housing and Area Development Authority (MHADA)

Housing Authority
Building Permit
Survey no. 12 pt bldg 113, plot 98

The promised possession date (30 Jun 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Maharashtra Housing and Area Development Authority (MHADA)

Planning authority

Has approved 438 RERA projects2.2% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
341
On record
13,458 flats · 0 plots
Reach
18 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by MahaRERA

07

Other projects nearby

The register · within 25 km

4,199 residential projects still under way within 25 km. Step out ring by ring:

43 projects within 1 km — showing the nearest 6.

KurlaResidential / Group Housing

OM NANDADEEP CO-OP. HSG. SOC. LTD.

OM NANDADEEP CO-OP HOUSING SOCIETY LIMITED

Jan 2024registered
Oct 2026target completion
Scale65 flatsAuthorityMahaRERA
KurlaResidential / Group Housing

SAYBA ELEGANT

STAR AURA

Jul 2023registered
Mar 2026target completion
Scale115 flatsAuthorityMahaRERA
KurlaMixed

SAYBA CRYSTAL

AMOOL ENTERPRISES

Jul 2024registered
May 2027target completion
Scale185 flatsAuthorityMahaRERA
KurlaResidential / Group Housing

SAYBA ROYAL

M/S. STAR RISE

Jan 2025registered
Dec 2026target completion
Scale152 flatsAuthorityMahaRERA
KurlaMixed

Sayba Iris

STAR RISE

Jan 2026registered
Jan 2029target completion
1 open complaintScale151 flatsAuthorityMahaRERA
KurlaResidential / Group Housing

152 Samruddhi

Aditya Samruddhi Enterprises

Nov 2025registered
Dec 2029target completion
AuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. This project’s coordinate is approximate, so distances are rough.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.